Contract
No: HK/2011/07 Wanchai Development Phase
II and Sampling, Field Measurement and
Testing Works
(Stage 2) Environmental Permit no. EP-356/2009, Further Evironmental permit nos.
fep-01/356/2009, fep-02/356/2009, FEP-03/356/2009, Fep-04/356/2009 and Fep-05/356/2009 Monthly Environmental Monitoring & Audit Report
- March 2012 -
|
CLIENTS: |
|
Civil Engineering and Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point Wanchai, H.K. Telephone:
(852) 2882-3939 Facsimile:
(852) 2882-3331 E-mail:
info@lamenviro.com Website:
http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
Raymond
Dai Environmental
Team Leader |
|
DATE: |
|
16 April 2012 |
2.2 Scope of the Project and Site Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact Personnel
3. Status of Regulatory Compliance
3.1 Status of Environmental Licensing and Permitting under
the Project
5.2 Real-time Noise Monitoring
6.2 Real-time noise Monitoring
6.5 Review of the Reasons for and the Implications of
Non-compliance
6.6 Summary of action taken in the event of and follow-up
on non-compliance
7. Cumulative Construction Impact due to the Concurrent
Projects
9. Complaints,
Notification of Summons and Prosecution
lIST OF TABLES
Table I Summary
of Water Quality Monitoring Exceedances in Reporting Month
Table II Summary
of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month
Table 2.1 Schedule
2 Designated Projects under this Project
Table 2.2 Details
of Individual Contracts under the Project
Table 2.3 Contact
Details of Key Personnel
Table 3.2 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/11
Table 3.3 Summary
of submission status under FEP-01/356/2009 Condition
Table 3.4 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Table 3.5 Summary
of submission status under FEP-02/356/2009 Condition
Table 3.6 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/02
Table 3.7 Summary
of submission status under FEP-03/356/2009 Condition
Table 3.8 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/15
Table 3.9 Summary
of submission status under FEP-04/356/2009 Condition
Table 3.10 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2010/06
Table 3.11 Summary
of submission status under EP-356/2009 and FEP-05/356/2009 Condition
Table 3.12 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/19
Table 4.1 Noise
Monitoring Station
Table 4.2 Real
Time Noise Monitoring Station
Table 4.3 Air
Monitoring Station
Table 4.4 Marine
Water Quality Stations for Water Quality Monitoring
Table 4.5 Marine
Water Quality Monitoring Frequency and Parameters
Table 4.6 Marine
Water Quality Stations for Enhanced Water Quality Monitoring
Table 4.7 Marine
Water Quality Stations for Additional DO Monitoring
Table 5.1 Noise
Monitoring Stations for Contract no. HY/2009/11
Table 5.2 Noise
Monitoring Station for Contract nos. HK/2009/01, HK/2009/02 and HK/2010/06
Table 5.3 Noise
Monitoring Station for Contract no. HY/2009/15
Table 5.4 Noise
Monitoring Station for Contract no. HY/2009/19
Table 5.5 Real
Time Noise Monitoring Station for Contract no. HY/2009/11 and HY/2009/19
Table 5.6 Air
Monitoring Stations for Contract no. HY/2009/11
Table 5.7 Air
Monitoring Stations for Contract no. HK/2009/01
Table 5.8 Air
Monitoring Station for Contract no. HK/2009/02
Table 5.9 Air
Monitoring Station for Contract no. HY/2009/15
Table 5.10 Air Monitoring Stations for
Contract no. HY/2009/19
Table 5.11 Water Monitoring Stations
for Contract no. HY/2009/11
Table 5.12 Water Monitoring Stations
for Contract no. HK/2009/01
Table 5.13 Water Monitoring Stations
for Contract no. HK/2009/02
Table 5.14 Water Monitoring Stations
for Contract no. HK/2010/06
Table 5.15 Water Monitoring Stations
for Contract no. HY/2009/15
Table 5.16 Water Monitoring Stations
for Contract no. HY/2009/19
Table 5.17 Summary of Water Quality
Monitoring Exceedances in Reporting Month
Table 5.18 Summary of Enhanced
Dissolved Oxygen Monitoring Exceedances in Reporting Month
Table 5.19 Details
of Waste Disposal for Contract no. HK/2009/01
Table 5.20 Details
of Waste Disposal for Contract no. HK/2009/02
Table 5.21 Details
of Waste Disposal for Contract no. HY/2009/15
Table 5.22 Details
of Waste Disposal for Contract no. HK/2010/06
Table 8.1 Summary
of Environmental Inspections for Contract no. HK/2009/01
Table 8.2 Summary
of Environmental Inspections for Contract no. HK/2009/02
Table 8.3 Summary
of Environmental Inspections for Contract no. HY/2009/15
Table 8.4 Summary
of Environmental Inspections for Contract no. HK/2010/06
Table 8.5 Summary
of Environmental Inspections for Contract no. HY/2009/19
Table 9.1 Cumulative
Statistics on Complaints
Table 9.2 Cumulative
Statistics on Successful Prosecutions
Table 10.1 Construction
Activities and Recommended Mitigation Measures in Coming Reporting Month
lIST
OF FIGUREs
Figure 2.2 Project Organization Chart
Figure 2.3 Locations of
Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 3.1 Environmental Mitigation
Implementation Schedule
Appendix 4.1 Action and Limit
Level
Appendix 4.2 Copies of
Calibration Certificates
Appendix 5.1 Monitoring
Schedule for Reporting Month and Coming month
Appendix 5.2 Noise Monitoring Results and Graphical Presentations
Appendix 5.3 Air Quality Monitoring Results and Graphical Presentations, and Odour Patrol
Results
Appendix 5.4 Water Quality Monitoring Results and Graphical Presentations
Appendix 5.4a Additional
Dissolved Oxygen Monitoring Results
Appendix 5.5 Real-time Noise Monitoring Results and Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix 6.2 Summary for Notification
of Exceedance
Appendix 8.1 Construction Programme
of Individual Contracts
Construction Activities for the Reported Period
¡P
The major work activities for Contract no. HY/2009/11 was confirmed substantial
complete by RSS on 4 January 2012. The construction site was handed over to
contractor HY/2009/19 on 31 December 2011.
Marine Works
¡P
Dredging works within HKCEC water Channel form CH190 to Ch260 for Type
2
sediment
¡P
Dredging works within HKCEC Water Channel from CH190 to CH260 for Type
3
sediment
¡P
Installation of sheet pile for cooling water intake at Dome Promenade
between CH120 and CH170
¡P
Seawall reinstatement and retaining wall construction at Wan Chai
Lanfill in Zone B1-3
¡P
Preparation works for demolition of existing seawall at
Cross-harbour Watermains
Installation
¡P
Installation of cross-harbour watermains nos. A16/B16
¡P
Rockfilling and rock protection for cross-harbour watermains
¡P
Grouting works at TST seafront along the pipe pile wall
¡P
Trench excavation and installation of shoring system along the pipe pile
wall at TST seafront
¡P
Dredging works in confined water by 9 in 1 barge
Fresh
Watermains, Cooling Watermains and Salt Watermains (On Land)
¡P
Mainlaying works at Zone B1-3, B1-6, B4-4, B5-3, A1-1, A2-3C1, A3-3,
A3-4B, A3-5B and A4-2A
¡P
Mainlaying works and subsequent carriageway reinstatement in Zone A2-2
and A1-5A
¡P
Mainlaying at Zone A3-4B
¡P
Diversion of unferground cables at footpath of
¡P
Mainlaying Works at Zone A2-3C1 and subsequent road reinstatement work
¡P
Cable ducting works along
¡P
Cable ducting works along
¡P
Cable ducting works along
¡P
Heading No. H7 and H8 (mainlaying woks by trenchless method)
¡P
Mainlaying and chamber
construction works at the traffic island near junction of
¡P
Trench excavation, pipe layig works and chamber construction for a 1000
dia. watermains (CHF) at
¡P
Trench excavation, pipe laying works and chamber construction for a 1000
dia. watermains (CHE) at
¡P
Pipe installation by trenchless method across the EVA near
¡P
300mm thick topping slab at southern portion and helipad slab
¡P
Lighting installation at Helipad
¡P
Panel of Safety Net at Helipad
¡P
Hydraulics pipe and hydraulics pump installation
¡P
ABWFs and E&M works of Passenger Terminal Building (PTB)
¡P
Installation of glass wall at PTB
¡P
Drilling hole of holding down bolt on existing pier deck at Noise
Barrier NB2
¡P
Concreting the footing of Noise Barrier NB1
¡P
Concreting the drain pipe (150mm dia.) from manhole N7.3 to N1.2 and
manhole N7.3 wall stem and top slab of EVA at
¡P
Breaking up the cover walkway footing of EVA at
¡P
E&M works of P7, P8 & P9
¡P
-0.85mPD steel platform of P7, P8 & P9 installation
¡P
+1.35mPD and -0.85mPD steel platform substantially completed at P7, P8
& P9 and handover to E & M Team for next stage of work.
¡P
Wet Well penstock installation substantially was ongoing at P7, P8 &
P9 and commences to install the traveling band screen.
¡P
36 concrete pipes of DSD pipe jacking drive in TBM
¡P
Annulus chemical grout surrounding the steel sleeve
¡P
Excavation and lateral support of the Jacking pit at ex-pet garden for
the cooling mains construction across HHR.
¡P
Approximate 60m cooling water pipe was laid at Harbour Centre,
¡P
Approximate 15m cable duct was laid at
¡P
Casting of slab above HEC room @ +9.17mPD for the WSD Salt Water Pumping
Station.
¡P
Excavation for installation of 3rd layer (-1.5mPD) struts & wailings
for shoring system of 610 pipe pile wall landside cofferdam of salt water
intake culvert.
¡P
Excavation for installation of 2nd layer (+0.5mPD) struts & wailings
for shoring system of salt water intake culvert Seaside Cofferdam.
¡P
Dismantle of temporary water tank at Portion 1A was in progress. Installation
of temporary water tank for construction of pile caps & beams at Portion 1A.
¡P
Fabrication of temporary water tank at Portion 2A & 2B formwork and
re-bars fixing for lower portion caps and beams at Portion 1A of New Ferry Pier.
¡P
Installation of temporary water tank for construction of pile caps &
beams at Portion 2B.
¡P
Welding of steel supports at Portion 2C of the New Ferry Pier.
¡P
Backfilling on the HDPE pipelines at diffuser section between CH0 & CH150
¡P
Excavation for installation of 3rd layer (-2.0mPD) struts & wailings
for shoring system of Submarine Outfall Seaside Cofferdam
¡P
Installation of Temporary Decking Platform "C"
¡P
Reclamation works at TS4/ME4
¡P
Diaphragm wall construction preparation works at TS4
¡P
Marine SI at TS2
¡P
ELS works at TS1 and TPCWAE
¡P
Night time protection works at CHT
¡P
Cut off wall preparation works at
¡P
Excavation of bored piles
¡P
Concreting of bored piles
¡P
Coring Works
¡P
Sheet Piles
¡P
Construction of Pre-cast Unit in
¡P
Marine bored piling
Noise Monitoring
Real-time Noise Monitoring
Air Quality Monitoring
CMA1b: from 13 Mar 2012 to 14 Mar 2012
CMA3a: from 24 Mar 2012 to 26 Mar 2012
Water Quality Monitoring
Table
I Summary of Water Quality
Monitoring Exceedances in Reporting Month
Contract no. |
Water Monitoring
Station |
Mid-flood |
Mid-ebb |
|||||||||||
DO |
Turbidity |
SS |
DO |
Turbidity |
SS |
|||||||||
|
LL |
|
LL |
|
LL |
|
LL |
|
LL |
|
LL |
|||
HY/2009/11 |
WSD9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Monitoring finished on 6 Feb 2012 |
WSD10 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
WSD15 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
WSD17 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C8 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HK/2009/01 |
WSD19 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
1 |
|
|
WSD20 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
|
|
WSD7 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C3 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C4e |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C4w |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HK/2009/01 & HK/2010/06 |
C2 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HK/2009/02 |
C5e |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C5w |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
WSD21 |
0 |
0 |
1 |
1 |
0 |
1 |
0 |
0 |
2 |
1 |
1 |
0 |
|
Monitoring started on 8 Feb 2012 |
WSD9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Monitoring started on 8 Feb 2012 |
WSD17
|
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
1 |
0 |
1 |
|
HY/2009/15 |
C7 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
|
HY/2009/19 Monitoring started on 28 Jan 2012 |
C8 |
0 |
0 |
1 |
1 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
|
C9 |
0 |
0 |
0 |
3 |
3 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
||
Total |
0 |
0 |
3 |
5 |
7 |
3 |
0 |
0 |
3 |
4 |
1 |
2 |
||
Remarks: - The cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated since 17 May 2011.
- WSD9 and WSD17 were implemented with respect to HK/2009/02 from 8 Feb 2012.
-
4-week water quality monitoring at WSD9, WSD10, WSD15, WSD17, C8 and C9
were completed on 6 Feb 2012.
-
C8 and C9 were implemented with respect to HY/2009/19 from 28 Jan 2012.
Table
II Summary of Enhanced Dissolved
Oxygen Monitoring Exceedances in Reporting Month
Contract no. |
Water Monitoring Station |
Mid-flood |
Mid-ebb |
||
DO |
DO |
||||
|
LL |
|
LL |
||
HY/2009/15 |
C6 |
0 |
0 |
0 |
0 |
C7 |
0 |
0 |
0 |
0 |
|
Ex-WPCWA SW |
0 |
0 |
0 |
0 |
|
Ex-WPCWA SE |
0 |
0 |
0 |
0 |
|
Total |
0 |
0 |
0 |
0 |
Complaints, Notifications of Summons and Successful Prosecutions
Site Inspections and Audit
Future Key Issues
Contract no. HY/2009/11- North Point
Reclamation
¡P
The major work activities for Contract no. HY/2009/11 was confirmed
substantial complete by RSS on 4 January 2012. The construction site was handed
over to contractor HY/2009/19 on 31 December 2011.
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
Marine Works
¡P
Dredging for CH160 to CH260 for subsequent reclamation within HKCEC
water Channel
¡P
Reclamation works and installation of sheet pile water channel (from
CH170 to CH260) would be commenced upon completed of dredging form CH160 to CH260
within HKCEC water Channel.
¡P
Rockfilling within HKCEC Water Channel (form CH220 to CH260)
¡P
Seawall reinstatement at WC landfall section
¡P
Dredging form CH290 to CH400 (stage 3) near
¡P
Installation of excavation and lateral support for modification of
vertical seawall near
Cross-harbour Watermains Installation
¡P
Ground treatment works along the pipe pile wall at TST seafront would be
continued and anticipated to be completed.
¡P
Trench excavation and installation of shoring system along the pipe pile
wall at TST seafront
¡P
Installation of cross-harbor watermains nos. A17/B17
¡P
Rockfilling protection works for cross-harbour watermians in
Fresh Watermains, Cooling Watermains and Salt
Watermains (On Land)
¡P
Works would be continued at Zone B1-3, B1-6, B4-4, A1-1, A3-3, A3-4B,
A3-5B,and A4-2A.
¡P
Trench excavation at Zone B5-3 would be completed and the subsequent
trench excavation at Zone B5-3B and B5-2B
¡P
Trench excavation at Zone B2-1 would be commenced right after the Third
Term Chief Executive Election held at HKCEC.
¡P
Mainlaying works at Zone B1-3 and Zone B1-6
¡P
Jacking pit construction at Zone A1-3
¡P
Heading No. H6 (toward western direction)
¡P
Mainlaying works at Zone A2-2
¡P
Heading No. 6 (toward eastern direction) would be commenced right after
a jacking pit was completed at A2-2.
¡P
Mainlaying works at traffic island near junction between
¡P
Heading Nos. H7 and H8
¡P
Cable ducting works at
Contract no. HK/2009/02 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
¡P
Continue operation of Tseung Kwan O Public Fill Sorting Facility.
¡P
Continue E&M works and ABWF works of passenger terminal.
¡P
Continue the T&C work of passenger terminal.
¡P
Continue remaining 300mm thick slab construction, foam system, lighting,
oil interceptor and guard house installation and E&M works at
¡P
Continue Noise Barrier NB1 and NB2 main frame and panel installation at
¡P
Continue d steel platforms installation at -0.85mPD for P8 & P9
Pumping Stations.
¡P
Continue steel platforms (Wet Well) installation at +2.2mPD for P7, P8
& P9 Pumping Stations.
¡P
Completed DSD 1 pipe jacking drive in TBM.
¡P
Commence DSD 2 pipe jacking drive in TBM.
¡P
Continue trench excavation and pipe laying works along
¡P
Continue trenchless excavation for the cooling mains connection between
¡P
Complete construction from + 11.63mPD to + 15.71mPD or WSD Salt Water
Pumping Station.
¡P
Continue 800MS pipe installation inside
¡P
Continue 800MS jacking pit excavation for the crossing under
¡P
Continue ABWFs & E&M works of WSD Salt Water Pumping Station.
¡P
Continue excavation works of seaside cofferdams for salt water intake
culvert, submarine outfall and Box Culvert N1.
¡P
Continue excavation works of landside cofferdam for the construction of
Bay 6 ¡V 10 salt water intake culverts.
¡P
Continue substructure works for the New Ferry Pier at Portions 1A, 2A,
2B, 2C & 3C.
¡P
Complete the fabrication of precast slabs for the New Ferry Pier in PRC
casting yard.
¡P
Installation of precast domes and end caps at the diffuser section of
the HDPE pipelines.
¡P
Complete backfilling rockfills for the installed submarine outfall pipes
and diffuser section and commence precast dome installation.
¡P
Continue installation of the temporary water diversion piping at WCR2
area.
¡P
Complete pre-bored H-piles construction at Box Culvert O.
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (
¡P
Diaphragm wall construction at TS4
¡P
ELS works at TS1 and TPCWAE
¡P
Night time protection works at CHT
¡P
Cut off wall preparation works at
¡P
Dredging for seawall foundation at TS2
¡P
Excavation of bored piles
¡P
Concreting of bored piles
¡P
Coring Works
¡P
Sheet Piles
¡P
Construction of Pre-cast Unit in
Contract no. HY/2009/19- Wan Chai Bypass Tunnal
(North Point Section) and Island Eastern Corridor Link
¡P
Marine bored piling
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed to
work as the Environmental Team (ET) under Environmental Permit no. EP-356/2009
and Further Environmental permit nos. FEP-01/356/2009, FEP-02/356/2009,
FEP-03/356/2009, FEP-04/356/2009 and FEP-05/356/2009 to implement the
Environmental Monitoring and Audit (EM&A) programme as stipulated in the
EM&A Manual of the approved Environmental Impact Assessment (EIA) Report
for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.:
AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for
Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No.
AEIAR-014/2001).
1.1.2.
This report presents the environmental monitoring
and auditing work carried out in accordance to the Section 10.3 of EM&A
Manual and ¡§Environmental Monitoring and Audit Requirements¡¨ under
Particular Specification Section 27.
1.1.3.
This report documents the finding of EM&A works
for Environmental Permit no. EP-356/2009, Further Environmental Permit no.
FEP-01/356/2009, FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009 and
FEP-05/356/2009 and during the period of February to March. The cut-off date of
reporting is at 27th of each reporting month.
Section
1 Introduction ¡V
details the scope and structure of the report.
Section
2 Project
Background ¡V summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section
3 Status of Regulatory Compliance ¡V
summarizes the status of valid Environmental Permits / Licenses during the
reporting period.
Section
4 Monitoring
Requirements ¡V summarizes all monitoring parameters,
monitoring methodology and equipment, monitoring locations, monitoring
frequency, criteria and respective event and action plan and monitoring
programmes.
Section
5 Monitoring
Results ¡V summarizes the monitoring results
obtained in the reporting period.
Section
6 Compliance
Audit ¡V summarizes the auditing of monitoring
results, all exceedances environmental parameters.
Section
7 Cumulative Construction Impact due to the Concurrent
Projects ¡V summarizes the relevant cumulative construction
impact due to the concurrent activities of the concurrent Projects.
Section
8 Site Inspection ¡V
summarizes the findings of weekly site inspections undertaken within the
reporting period, with a review
of any relevant
follow-up actions
within the reporting period.
Section
9 Complaints, Notification of summons and Prosecution
¡V summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section
10 Conclusion
2.1.1.
¡§Wan Chai Development phase II and Central-Wan Chai
Bypass¡¨ and ¡§Central-Wan Chai Bypass and Island Eastern Corridor Link¡¨
(hereafter called ¡§the Project¡¨) are Designed Project (DP) under the
Environmental Impact Assessment Ordinance (Cap. 499) (EIAO). The Environmental
Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and
2.1.2.
The key purpose of Wan Chai Development Phase II
(WDII) is to provide land at Wan Chai North and North Point for construction of
the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed
under the project will be developed as a world-class waterfront promenade
joining that at the new Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for the CWB
to provide relief to the very congested
2.2.1.
The Project is located mainly in Wan Chai North,
2.2.2.
The study area encompasses existing developments
along the Wan Chai,
2.2.3.
The scope of the Project
comprises:
¡P
Land formation
for key transport infrastructure and facilities, including the Trunk Road (i.e. CWB) and the associated
slip roads for connection to the Trunk Road and for through traffic from Central to
Wan Chai and Causeway Bay. The land formed for the above transport infrastructure
will provide opportunities for the development of an attractive waterfront
promenade for the enjoyment of the public
¡P
Reprovisioning /
protection of the existing facilities and structures affected by the land
formation works mentioned above
¡P
Extension, modification,
reprovisioning or protection of existing storm water drainage outfalls,
sewerage outfalls and watermains affected by the revised land use and land
formation works mentioned above
¡P
Upgrading of
hinterland storm water drainage system and sewerage system, which would be
rendered insufficient by the land formation works mentioned above
¡P
Provision of the
ground level roads, flyovers, footbridges, necessary transport facilities and
the associated utility services
¡P
Construction of
the new waterfront promenade, landscape works and the associated utility
services
¡P
The Trunk Road
(i.e. CWB) within the study area and the associated slip roads for connection
to the Trunk Road.
2.2.4.
The project also contains various Schedule 2 DPs
that, under the EIAO, require Environmental Permits (EPs) to be granted by the
DEP before they may be either constructed or operated. Table 2.1
summarises the five individual DPs under this Project. Figure 2.1 shows the
locations of these Schedule 2 DPs.
Table 2.1 Schedule
2 Designated Projects under this Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due to the multi-contract nature of the Project,
there are a number of contracts sub-dividing the whole works area into
different work areas to be commenced. Contractors of individual contracts will
be required by the EP holder to apply Further Environmental Permits (FEP) such
that the impact monitoring stations are sub-divided accordingly to facilitate
the implementation of EM&A programme and to streamline the EM&A
reporting for individual FEP holders correspondingly.
2.3.2.
The details of individual contracts are summarized
in Table 2.2.
Table 2.2 Details
of Individual Contracts under the Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction
Commencement Date |
HK/2009/01 |
Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at |
DP3, DP6 |
23 July 2010 |
DP1, DP2 |
25 August 2011 |
||
HK/2009/02 |
Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai
East |
DP3, DP5 |
5 July 2010 |
DP1 |
26 April 2011 |
||
HY/2009/11 |
Wan Chai Development Phase II and Central ¡V Wan Chai Bypass ¡V North
Point Reclamation |
DP3 |
17 March 2010 (Under application of surrender) |
HY/2009/15 |
Central-Wanchai Bypass ¡V Tunnel ( |
DP3 |
10 November 2010 |
DP1 |
13 July 2011 |
||
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near |
DP1 |
September 2010 |
HY/2009/17 |
Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced
piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central - Wan Chai Bypass (CWB) ¡V Central Interchange |
DP1 |
21 April 2011 |
HY/2009/19 |
Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
2.4.1.
Civil Engineering and Development Department and
Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively. For the
construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The proposed project organization and lines of
communication with respect to environmental protection works are shown in Figure 2.2. Key personnel and contact particulars are
summarized in Table 2.3:
Table
2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3916 1818 |
3529 2829 |
|
|
Contractor under Contract no. HY/2009/11 |
Project Director |
Mr. Cho Yu Fun |
3157 1086 |
3157 1085 |
Project Manager |
Mr. Gregory Wong |
3157 1086 |
|||
Site Agent |
Mr. Daniel Cheung |
3157 1086 |
|||
Environmental Officer |
Mr. C. M. Wong |
3157 1086 |
|||
Chun Wo ¡V Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Project Director |
|
9124 2471 |
2634 1626 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
|||
Operation Manager |
Mr. Lau Yee Ching |
9466 3918 |
|||
Construction Manager |
Mr. Wyman Wong |
9627 2467 |
|||
Construction Manager |
Mr. Jack Chu |
9775 3008 |
|||
Construction Manager |
Mr. KK Yuen Mr. Andy Yu |
9498 1213 96484896 |
|||
Environmental Officer
(Compliance Manager) |
Mr. Andy Mak |
9103 2370 |
|||
Chun Wo ¡V CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Project Manager |
Mr. Chan Sing Cho |
3658 3002 |
2827 9996 |
Site Agent |
Mr. Mak Kam Wing |
3658 3044 |
|||
Quality & Environmental Manager |
Mr. C.P. Ho |
3658 3000 |
|||
Environmental Officer |
Ms. Flora Ng |
3658 3064 |
|||
|
Contractor under Contract no. HY/2009/15 |
Project Manager |
Mr. M Y Wong |
2823 7879 |
2528 5651 |
Site Manager |
Mr. P J Fan |
3557 6368 |
2566 2192 |
||
|
|
Construction Manager |
Mr. C K Kwok |
3557 6393 |
2566 2192 |
|
|
Construction Manager (East) |
Gene Cheung |
3557 6395 |
2566 2192 |
|
|
Construction Manager (West) |
Tony Chiu |
9090 0606 |
|
|
|
Environmental Officer |
Mr. Daniel Sin |
3557 6215 |
|
Gammon -Leader JV |
Contractor under Contract no. HK/2010/06 |
Project Manager |
Mr. Paul Lui |
9095 7922 |
2529 2880 |
Site Agent |
Mr. Keith Tse |
2529 2068 |
|||
Environmental Officer |
Mr. Lee Wai Man |
9481
6024 |
|||
Chun Wo - CRGL - MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. Rayland Lee |
3758 8879 |
2570 8013 |
Site Agent |
Mr. Cheung Kit Cheung |
6909 1555 |
|||
Environmental Engineer |
Mr. Simon Wong |
9281 4346 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Construction Manager (Marine) |
William Luk |
9610 1101 |
|||
Construction Manager (Land) |
Patrick Cheung |
9643 3012 |
|||
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent Environmental Checker (IEC) |
Mr. David Yeung |
3743 0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3.
The major work activities for Contract no.
HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The
construction site was handed over to contractor HY/2009/19
on 31 December 2011.
2.4.4.
For Contract no. HK/2009/01, the principal work
activities in this reporting month included:
Marine Works
¡P
Dredging works within HKCEC water Channel form CH190 to Ch260 for Type
2
sediment
¡P
Dredging works within HKCEC Water Channel from CH190 to CH260 for Type
3
sediment
¡P
Installation of sheet pile for cooling water intake at Dome Promenade
between CH120 and CH170
¡P
Seawall reinstatement and retaining wall construction at Wan Chai
Lanfill in Zone B1-3
¡P
Preparation works for demolition of existing seawall at
Cross-harbour Watermains Installation
¡P
Installation of cross-harbour watermains nos. A16/B16
¡P
Rockfilling and rock protection for cross-harbour watermains
¡P
Grouting works at TST seafront along the pipe pile wall
¡P
Trench excavation and installation of shoring system along the pipe pile
wall at TST seafront
¡P
Dredging works in confined water by 9 in 1 barge
Fresh Watermains, Cooling Watermains and Salt
Watermains (On Land)
¡P
Mainlaying works at Zone B1-3, B1-6, B4-4, B5-3, A1-1, A2-3C1, A3-3, A3-4B,
A3-5B and A4-2A are in progress.
¡P
Mainlaying works and subsequent carriageway reinstatement in Zone A2-2
and A1-5A were completed.
¡P
Mainlaying at Zone A3-4B were commenced.
¡P
Diversion of unferground cables at footpath of
¡P
Mainlaying works at Heading No. 5 and Zone A1-4A were completed and
subsequent road reinstatement works was in progress.
¡P
Mainlaying Works at Zone A2-3C1 was completed and subsequent road
reinstatement work was in progress.
¡P
Cable ducting works along
¡P
Cable ducting works along
¡P
Cable ducting works along
¡P
Heading No. H7 and H8 (mainlaying woks by trenchless method) were in progress.
¡P
Mainlaying and chamber construction works at the traffic island near
junction of
¡P
Trench excavation, pipe layig works and chamber construction for a 1000
dia. watermains (CHF) at
¡P
Trench excavation, pipe laying works and chamber construction for a 1000
dia. watermains (CHE) at
¡P
Pipe installation by trenchless method across the EVA near
2.4.5.
For Contract no. HK/2009/02, the principal work
activities in this reporting month included:
¡P
300mm thick topping slab at southern portion and helipad slab
¡P
Lighting installation at Helipad
¡P
Panel of Safety Net at Helipad
¡P
Hydraulics pipe and hydraulics pump installation
¡P
ABWFs and E&M works of Passenger Terminal Building (PTB)
¡P
Installation of glass wall at PTB
¡P
Drilling hole of holding down bolt on existing pier deck at Noise
Barrier NB2
¡P
Concreting the footing of Noise Barrier NB1
¡P
Concreting the drain pipe (150mm dia.) from manhole N7.3 to N1.2 and
manhole N7.3 wall stem and top slab of EVA at
¡P
Breaking up the cover walkway footing of EVA at
¡P
E&M works of P7, P8 & P9
¡P
-0.85mPD steel platform of P7, P8 & P9 installation
¡P
+1.35mPD and -0.85mPD steel platform substantially completed at P7, P8
& P9 and handover to E & M Team for next stage of work.
¡P
Wet Well penstock installation substantially was ongoing at P7, P8 &
P9 and commences to install the traveling band screen.
¡P
36 concrete pipes of DSD pipe jacking drive in TBM
¡P
Annulus chemical grout surrounding the steel sleeve
¡P
Excavation and lateral support of the Jacking pit at ex-pet garden for
the cooling mains construction across HHR.
¡P
Approximate 60m cooling water pipe was laid at Harbour Centre,
¡P
Approximate 15m cable duct was laid at
¡P
Casting of slab above HEC room @ +9.17mPD for the WSD Salt Water Pumping
Station.
¡P
Excavation for installation of 3rd layer (-1.5mPD) struts & wailings
for shoring system of 610 pipe pile wall landside cofferdam of salt water
intake culvert.
¡P
Excavation for installation of 2nd layer (+0.5mPD) struts & wailings
for shoring system of salt water intake culvert Seaside Cofferdam.
¡P
Dismantle of temporary water tank at Portion 1A was in progress. Installation
of temporary water tank for construction of pile caps & beams at Portion 1A.
¡P
Fabrication of temporary water tank at Portion 2A & 2B formwork and
re-bars fixing for lower portion caps and beams at Portion 1A of New Ferry Pier.
¡P
Installation of temporary water tank for construction of pile caps &
beams at Portion 2B.
¡P
Welding of steel supports at Portion 2C of the New Ferry Pier.
¡P
Backfilling on the HDPE pipelines at diffuser section between CH0 & CH150
¡P
Excavation for installation of 3rd layer (-2.0mPD) struts & wailings
for shoring system of Submarine Outfall Seaside Cofferdam
¡P
Installation of Temporary Decking Platform "C"
2.4.6.
For Contract no. HY/2009/15, the principal work activities
in this reporting month included:
¡P
Reclamation works at TS4/ME4
¡P
Diaphragm wall construction preparation works at TS4
¡P
Marine SI at TS2
¡P
ELS works at TS1 and TPCWAE
¡P
Night time protection works at CHT
¡P
Cut off wall preparation works at
2.4.7.
For Contract no. HK/2010/06, the principal work
activities in this reporting month included:
¡P
Excavation of bored piles
¡P
Concreting of bored piles
¡P
Coring Works
¡P
Sheet Piles
¡P
Construction of Pre-cast Unit in
2.4.8.
For Contract no. HY/2009/19, the principal work
activity in this reporting month included:
¡P
Marine bored piling
2.4.9.
In coming reporting month, the principal work
activities of individual contracts are anticipated as follows:
Contract no. HY/2009/11- North Point Reclamation
¡P
The major work
activities for Contract no. HY/2009/11 was confirmed substantial complete by
RSS on 4 January 2012. The construction site was handed over to contractor HY/2009/19 on 31 December 2011.
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
Marine Works
¡P
Dredging for CH160 to CH260 for subsequent reclamation within HKCEC
water Channel
¡P
Reclamation works and installation of sheet pile water channel (from
CH170 to CH260) would be commenced upon completed of dredging form CH160 to
CH260 within HKCEC water Channel.
¡P
Rockfilling within HKCEC Water Channel (form CH220 to CH260)
¡P
Seawall reinstatement at WC landfall section would be continued and was
anticipated to be completed.
¡P
Dredging form CH290 to CH400 (stage 3) near
¡P
Installation of excavation and lateral support for modification of
vertical seawall near
Cross-harbour Watermains Installation
¡P
Ground treatment works along the pipe pile wall at TST seafront would be
continued and anticipated to be completed.
¡P
Trench excavation and installation of shoring system along the pipe pile
wall at TST seafront would be continued and anticipated to be completed.
¡P
Installation of cross-harbor watermains nos. A17/B17
¡P
Rockfilling protection works for cross-harbour watermians in
Fresh Watermains, Cooling Watermains and Salt
Watermains (On Land)
¡P
Works would be continued at Zone B1-3, B1-6, B4-4, A1-1, A3-3, A3-4B,
A3-5B,and A4-2A.
¡P
Trench excavation at Zone B5-3 would be completed and the subsequent
trench excavation at Zone B5-3B and B5-2B would be commenced concurrently.
¡P
Trench excavation at Zone B2-1 would be commenced right after the Third
Term Chief Executive Election held at HKCEC.
¡P
Mainlaying works at Zone B1-3 and Zone B1-6 would be continued and anticipated
to be completed by end Apr 2012.
¡P
Jacking pit construction at Zone A1-3
¡P
Heading No. H6 (toward western direction) would be commenced
accordingly.
¡P
Mainlaying works at Zone A2-2
¡P
Heading No. 6 (toward eastern direction) would be commenced right after
a jacking pit was completed at A2-2.
¡P
Mainlaying works at traffic island near junction between
¡P
Heading Nos. H7 and H8
¡P
Cable ducting works at
Contract no. HK/2009/02 - Wan
Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
¡P
Continue operation of Tseung Kwan O Public Fill Sorting Facility.
¡P
Continue E&M works and ABWF works of passenger terminal.
¡P
Continue the T&C work of passenger terminal.
¡P
Continue remaining 300mm thick slab construction, foam system, lighting,
oil interceptor and guard house installation and E&M works at
¡P
Continue Noise Barrier NB1 and NB2 main frame and panel installation at
¡P
Continue d steel platforms installation at -0.85mPD for P8 & P9
Pumping Stations.
¡P
Continue steel platforms (Wet Well) installation at +2.2mPD for P7, P8
& P9 Pumping Stations.
¡P
Completed DSD 1 pipe jacking drive in TBM.
¡P
Commence DSD 2 pipe jacking drive in TBM.
¡P
Continue trench excavation and pipe laying works along
¡P
Continue trenchless excavation for the cooling mains connection between
¡P
Complete construction from + 11.63mPD to + 15.71mPD or WSD Salt Water
Pumping Station.
¡P
Continue 800MS pipe installation inside
¡P
Continue 800MS jacking pit excavation for the crossing under
¡P
Continue ABWFs & E&M works of WSD Salt Water Pumping Station.
¡P
Continue excavation works of seaside cofferdams for salt water intake
culvert, submarine outfall and Box Culvert N1.
¡P
Continue excavation works of landside cofferdam for the construction of
Bay 6 ¡V 10 salt water intake culverts.
¡P
Continue substructure works for the New Ferry Pier at Portions 1A, 2A,
2B, 2C & 3C.
¡P
Complete the fabrication of precast slabs for the New Ferry Pier in PRC
casting yard.
¡P
Installation of precast domes and end caps at the diffuser section of
the HDPE pipelines.
¡P
Complete backfilling rockfills for the installed submarine outfall pipes
and diffuser section and commence precast dome installation.
¡P
Continue installation of the temporary water diversion piping at WCR2
area.
¡P
Complete pre-bored H-piles construction at Box Culvert O.
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V
Tunnel (
¡P
Diaphragm wall
construction at TS4
¡P
ELS works at TS1
and TPCWAE
¡P
Night time
protection works at CHT
¡P
Cut off wall
preparation works at
¡P
Dredging for
seawall foundation at TS2
Contract no. HK/2010/06 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass over MTR Tsuen Wan Line
¡P
Excavation of
bored piles
¡P
Concreting of
bored piles
¡P
Coring Works
¡P
Sheet Piles
¡P
Construction of
Pre-cast Unit in
Contract no. HY/2009/19 ¡V Central- Wan Chai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link
¡P
Marine bored
piling
3.1.1.
A summary of the current status on licences and/or
permits on environmental protection pertinent to the Project is shown in Table
3.1.
Permits and/or Licences |
Reference No. |
Issued Date |
Status |
Environmental
Permit |
EP-356/2009 |
30 Jul
2009 |
Valid |
Environmental
Permit |
EP-364/2009/A |
4 Aug
2010 |
Valid |
Environmental
Permit |
EP-364/2009 |
17 Aug
2009 |
Superseded |
Environmental
Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb
2010 |
Under
application of surrender |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar
2010 |
Valid |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar
2010 |
Valid |
Further
Environmental Permit |
FEP-04/356/2009 |
22 Nov
2010 |
Valid |
Further
Environmental Permit |
FEP-05/356/2009 |
24 Mar
2011 |
Valid |
Further
Environmental Permit |
FEP-01/364/2009 |
24 Mar
2010 |
Valid |
Further
Environmental Permit |
FEP-02/364/2009 |
21 Apr 2010 |
Valid |
Further
Environmental Permit |
FEP-03/364/2009 |
12 Jul 2010 |
Valid |
Further
Environmental Permit |
FEP-04/364/2009/A |
14 Oct 2010 |
Surrendered |
Further
Environmental Permit |
FEP-05/364/2009/A |
15 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-06/364/2009/A |
22 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-07/364/2009/A |
25 Feb 2011 |
Valid |
3.1.2.
Due to the multi-contract nature of the Project,
the status of permits and/or licences under the individual contract(s) are
presented as below:
Contract no. HY/2009/11 ¡V
Central ¡V Wanchai Bypass, North Point Reclamation
3.1.3.
The major work activities for Contract no.
HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The
construction site was handed over to contractor HY/2009/19 on 31
December 2011.
3.1.4.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission under
FEP-01/356/2009 for contract no. HY/2009/11 are shown in Table 3.2 and
Table 3.3.
3.1.5.
Contractor submitted a letter dated 20 July 2011 to
confirm that the dredging works and dumping operation were completed.
Table 3.2 Cumulative
Summary of Valid Licences and Permits
under Contract no. HY/2009/11
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
N/A |
Valid |
Notification of Works Under APCO |
331892 |
4 Jul. 2011 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-piling equipment |
GW-RS0922-11 |
12 Oct 2011 |
1 Nov 2011 to 30 Apr 2012 |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-151-C3631-02 |
12 Oct 2010 |
N/A |
Valid |
Billing Account under Waste Disposal Ordinance |
7010037 |
13 Jan 2010 |
N/A |
Valid |
Discharge Licence |
WT00007942-2010 |
29 Nov 2010 |
30 Nov 2015 |
Valid |
Table
3.3 Summary of submission status under
FEP-01/356/2009 Condition
EP Condition |
Submission |
Date of
Submission |
Condition 2.6 |
Management Organization of Main
Construction Companies |
18 Dec 2009 |
Condition 2.7 |
Submission of works schedule
and location plan |
8 Feb 2010 |
Condition 2.8 |
Revised Silt Curtain Deployment
Plan (Rev. 3) |
4 Dec 2010 |
Condition 2.9 |
Silt Screen Deployment Plan
(Rev. 6) |
18 May 2011 |
Condition 2.10 |
Coral Translocation Plan |
20 Nov 2009 |
Condition 2.16 |
Revised Noise Management Plan
(Rev 5) |
19 Feb 2011 |
Condition 2.17 |
Landscape Plan |
12 May 2010 |
|
Revised landscape Plan |
30 Jun 2010 |
|
Submission of Supplementary
Information - Revised Management & Maintenance Schedule for Submitted
Revised Landscape Plan |
25 Aug 2010 |
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
3.1.6.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission for contract no.
HK/2009/01 under FEP-02/356/2009 are shown in Table 3.4 and
Table 3.5.
Table
3.4 Cumulative Summary of Valid Licences
and Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
|
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
Notification of Works Under APCO |
313088 |
6 Jan 2010 |
N/A |
Valid |
Construction Noise
Permit (CNP) for non-piling equipment |
GW-RS0832-11 |
7 Sep 2011 |
03 Sep 2011 to 02 Mar 2012 |
Cancelled |
|
GW-RS0850-11 |
12 Sept 2011 |
14 Sept 2011 to 13 Mar 2012 |
Expired |
|
GW-RS0851-11 |
12 Sept 2011 |
16 Sept 2011 to 15 Mar 2012 |
Expired |
|
GW-RE0716-11 |
28 Sept 2011 |
07 Oct 2011 to 29 Mar 2012 |
Valid |
|
GW-RS1094-11 |
23 Nov 2011 |
27 Nov 2011 to 26 May 2012 |
Expired |
|
GW-RS1031-11 |
3 Nov 2011 |
7 Nov 2011 to 6 May 2012 |
Valid |
|
GW-RS1221-11 |
30 Jan 2011 |
20 Jan 2012 to 19 Jul 2012 |
Valid |
|
GW-RS1227-11 |
30 Dec 2011 |
30 Dec 2011 to 26 Jul 2012 |
Cancelled |
|
GW-RS0038-12 |
16 Jan 2012 |
15 Jan 2012 to 12 Jul 2012 |
Cancelled |
GW-RS0158-12 |
24 Feb 2012 |
24 Feb 2012 to 23 Aug 2012 |
Valid |
|
GW-RS0181-12 |
24 Feb 2012 |
27 Feb 2012 to 23 Aug 2012 |
Valid |
|
GW-RS0213-12 |
28 Feb 2012 |
29 Feb 2012 to 27 Aug 2012 |
Valid |
|
GW-RS0225-12 |
2 Mar 2012 |
14 Mar 2011 to 13 Sep 2012 |
Valid |
|
GW-RS0227-12 |
2 Mar 2012 |
16 Mar 2011 to 15 Sep 2012 |
Valid |
|
GW-RE0174-12 |
5 Mar 2012 |
30 Mar 2012 to 29 Sep 2012 |
Valid |
|
|
GW-RS0312-12 |
28 Mar 2012 |
30 Mar 2012 to 29 Sep 2012 |
Valid |
GW-RS-0314-12 |
29 Mar 2012 |
30 Mar 2012 to 25 Sep 2012 |
Valid |
|
Discharge Licence |
WT00006220-2010 |
18 Mar 2010 |
31 Mar 2015 |
Valid |
WT00009641-2011 |
24 Jul 2011 |
31 Jul 2016 |
Valid |
|
Billing account under Waste Disposal Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan 2010 |
N/A |
Valid |
Dumping Permit (Type 1 ¡V |
EP/MD/12-091 |
23 Nov 2011 |
24 Nov 2011 to 23 May 2012 |
Valid |
Dumping Permit (Type 1 ¡V |
EP-MD-12-120 |
8 Feb 2012 |
10 Feb 2012 to 9 Mar 2012 |
Expired |
|
EP-MD-12-136 |
8 Mar 2012 |
10 Mar 2012 to 9 Apr
2012 |
Valid |
Permit for Dumping at Sea - Dredged Sediment Requiring
Type 3 ¡V Special Treatment / Disposal contained in Geosynthetic Containers |
EP/MD/12-114 |
30 Jan 2012 |
30 Jan 2012 ¡V 29 Feb
2012 |
Expired |
Table
3.5 Summary of submission status under
FEP-02/356/2009 Condition
EP Condition |
Submission |
Date of
Submission |
Condition 2.6 |
Management Organization of Main Construction Companies |
13 Apr 2010 |
Condition 2.7 |
Works Schedule and Location
Plan |
8 Apr 2010 |
Condition 2.8 |
Silt Curtain Deployment Plan |
19 Apr 2010 |
Condition 2.9 |
Silt Screen Deployment Plan |
19 Apr 2010 |
Conditions 2.8 and 2.9 |
Supplementary Document on Silt
Curtain and Silt Screen Deployment Plan |
19 Jul 2010 |
Report on Field Testing for
Silt Curtain |
26 Aug 2010 |
|
Report on Field Testing for
Silt Curtain (Rev. A) |
15 Nov 2010 |
|
Condition 2.12(d) |
Alternative Proposal on
Concurrent Dredging for Sewage Pipeline and |
15 Apr 2011 |
Condition 2.17 |
Noise Management Plan |
23 Apr 2010 |
Condition 2.18 |
Landscape Plan (Erection of
Decorative Screen Hoarding along Construction Site around |
15 May 2010 |
Landscape Plan (Night-time
Lighting) |
22 Oct 2010 |
|
|
Landscape Plan (Rev. B) |
15 Nov 2010 |
Contract no. HK/2009/02 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
3.1.7.
Summary of the current
status on licences and/or permits on environmental protection pertinent and
submission for contract no. HK/2009/02 under FEP-03/356/2009 are shown in Table
3.6 and Table 3.7.
Table
3.6 Cumulative Summary of Valid Licences
and Permits under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
|
|
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
Notification of Works Under APCO |
313962 |
2 Feb 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for piling equipment |
PP-RS0007-12 |
27 Mar 2012 |
28 Mar 2012 to 27 Sept
2012 |
Valid |
Construction Noise Permit (CNP) for non-piling equipment |
GW-RS0833-11 |
8 Sept 2011 |
10 Sept 2011 to 4 Mar 2012 |
Cancelled |
|
GW-RE0710-11 |
30 Sept 2011 |
1 Nov 2011 to 30 Apr 2012 |
Valid |
|
GW-RS0918-11 |
7 Oct 2011 |
10 Oct 2011 to 9 Apr 2012 |
Valid |
|
GW-RS0930-11 |
11 Oct 2011 |
1 Nov 2011 to 30 Apr 2012 |
Valid |
|
GW-RS0931-11 |
7 Oct 2011 |
10 Oct 2011 to 9 Apr 2012 |
Valid |
|
GW-RS0941-11 |
20 Oct 2011 |
23 Nov 2011 to 22 May 2012 |
Valid |
|
GW-RS0955-11 |
14 Oct 2011 |
23 Nov 2011 to 22 May 2012 |
Valid |
|
GW-RS0968-11 |
20 Oct 2011 |
18 Nov 2011 to 17 May 2012 |
Valid |
|
GW-RS0983-11 |
24 Oct 2011 |
26 Oct 2011 to 23 April 2012 |
Cancelled |
|
GW-RS0984-11 |
25 Oct 2011 |
30 Oct 2011 to 27 April 2012 |
Valid |
|
GW-RS1028-11 |
3 Nov 2011 |
7 Dec 2011 to 6 June 2012 |
Valid |
|
GW-RS1052-11 |
18 Nov 2011 |
21 Nov 2011 to 18 May 2012 |
Valid |
|
GW-RS1111-11 |
28 Nov 2011 |
29 Nov 2011 to 28 May 2012 |
Valid |
|
GW-RS1116-11 |
28 Nov 2011 |
13 Dec 2011 to 12 Jun 2012 |
Valid |
|
GW-RS1209-11 |
3 Jan 2012 |
17 Jan 2012 to 16 July 2012 |
Valid |
|
GW-RS0037-12 |
19 Jan 2012 |
1 Feb 2012 to 31 July 2012 |
Valid |
|
GW-RS0051-12 |
19 Jan 2012 |
1 Feb 2012 to 31 July 2012 |
Valid |
|
GW-RS0052-12 |
19 Jan 2012 |
1 Feb 2012 to 30 April 2012 |
Valid |
GW-RS0086-12 |
30 Jan 2012 |
3 Feb 2012 to 2 Aug 2012 |
Valid |
|
GW-RS0105-12 |
3 Feb 2012 |
10 Feb 2012 to 9 Aug 2012 |
Valid |
|
GW-RS0153-12 |
17 Feb 2012 |
21 Feb 2012 to 20 Aug 2012 |
Valid |
|
GW-RS0233-12 |
6 Mar
2012 |
9 Mar 2012 to 8 Sept 2012 |
Cancelled |
|
GW-RS0255-12 |
14 Mar
2012 |
17 Mar 2012 to 15 Sept 2012 |
Valid |
|
GW-RS0298-12 |
22 Mar
2012 |
26 Mar 2012 to 25 June 2012 |
Valid |
|
|
GW-RS0301-12 |
20 Mar
2012 |
21 Mar 2012 to 20 Sept 2012 |
Valid |
GW-RS0303-12 |
26 Mar 2012 |
27 Mar 2012 to 27 Sept 2012 |
Valid |
|
Discharge Licence |
WT00006249-2010 |
22 Mar 2010 |
31 Mar 2015 |
Valid |
WT00006436-2010 |
15 Apr 2010 |
30 Apr 2015 |
Valid |
|
WT00006673-2010 |
14 May 2010 |
31 Mar 2015 |
Valid |
|
WT00006757-2010 |
28 May 2010 |
31 May 2015 |
Valid |
|
WT00007129-2010 |
28 July 2010 |
31 Jul 2015 |
Valid |
|
WT00008982-2011 |
26 April 2011 |
30 April 2016 |
Valid |
|
WT00009691-2011 |
1 Aug 2011 |
31 July 2016 |
Valid |
|
Billing Account under Waste Disposal Ordinance (Land) |
7010255 |
10 Feb 2010 |
N/A |
Valid |
Billing Account under Waste Disposal Ordinance (Marine) |
7011496 |
6 Oct 2010 |
N/A |
Valid |
Registration as Chemical Waste Producer (Wan Chai) |
WPN5213-135-C3593-01 |
10 Mar 2010 |
N/A |
Valid |
Registration as Chemical Waste Producer (TKO 137) |
WPN5213-839-C3593-02 |
22 Sep 2010 |
N/A |
Valid |
Dumping Permit (Type 1 ¡V |
EP/MD/12-082 |
31 Oct 2011 |
29 Nov 2011 to 28 May 2012 |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type
2 ¡V Confined Marine disposal) |
EP/MD/12-129 |
2 Mar 2012 |
4 Mar 2012 to 3 Apr 2012 |
Valid |
Table
3.7 Summary of submission status under
FEP-03/356/2009 Condition
EP Condition |
Submission |
Date of
Submission |
Condition 1.12 |
Commencement Date of Construction
of Marine Works |
8 April 2010 |
Condition 2.6 |
Management Organization of Main
Construction Companies |
10 April 2010 |
Condition 2.7 |
Works Schedule and Location
Plans |
8 April 2010 |
Condition 2.8 |
Silt Curtain Deployment Plan
(Revision A) |
20 April 2010 |
Silt Curtain Deployment Plan
(Revision B) |
25 May 2010 |
|
Silt Curtain Deployment Plan
(Revision C) |
14 Jun 2010 |
|
Silt Curtain Deployment Plan
(Revision H) |
15 Feb 2011 |
|
Silt Curtain Deployment Plan
(Revision I) |
17 Nov 2011 |
|
Silt Curtain Deployment Plan
(Revision J) |
15 Feb 2012 |
|
Condition 2.9 |
Silt Screen Deployment Plan |
21 April 2010 |
Supplementary Information for
Existing WSD Salt Water Intakes at |
5 Oct 2010 |
|
Silt Screen Deployment Plan
(Revision B) |
15 Feb 2012 |
|
Condition 2.17 |
Noise Management Plan |
6 May 2010 |
Condition 2.18 |
Landscape Plan (Decorative
Screen Hoarding) |
11 May 2010 |
Landscape Plan (Control of
Night Time Lighting) |
2 June 2010 |
|
Landscape Plan (Combined
Version) |
20 July 2011 |
|
Landscape Plan (Combined
Version) |
5 Aug 2011 |
|
----- |
Acknowledge of Submission |
22 Aug 2011 |
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V
Tunnel (
3.1.8.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission for contract no.
HY/2009/15 under EP-356/2009 are shown in Table 3.8 and
Table 3.9.
Table
3.8 Cumulative Summary of Valid Licences
and Permits under Contract no. HY/2009/15
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-04/356/2009 |
22 Nov 2010 |
N/A |
Valid |
FEP-06/364/2009/A |
22 Nov 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
321822 |
24 Sep 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-piling equipment |
GW-RS0820-11 |
5 Sep 2011 |
8 Sep 2011 to 7 Mar 2012 |
Expired |
|
GW-RS0883-11 |
4 Oct 2011 |
5 Oct 2011 to 4 Apr 2012 |
Valid |
|
GW-RS0997-11 |
2 Nov 2011 |
2 Nov 2011 to 2 May 2012 |
Valid |
|
GW-RS1021-11 |
4 Nov 2011 |
10 Nov 2011 to 9 May 2012 |
Valid |
|
GW-RS1138-11 |
7 Dec 2011 |
8 Dec 2011 to 21 May 2012 |
Valid |
|
GW-RS1153-11 |
9 Dec 2011 |
12 Dec 2011 to 16 Mar 2012 |
Cancelled |
|
GW-RS1211-11 |
22 Dec 2011 |
24 Dec 2011 to 21 Jun 2012 |
Valid |
|
GW-RS1149-11 |
6 Dec 2011 |
8 Dec 2011 to 7 Jun 2012 |
Cancelled |
|
GW-RS1190-11 |
30 Dec 2011 |
22 Dec 2011 to 21 Jun 2012 |
Valid |
|
GW-RS0150-12 |
22 Feb 2012 |
27 Feb 2012 to 24 Aug 2012 |
Valid |
GW-RS0094-12 |
1 Feb 2012 |
3 Feb 2012 to 31 Jul 2012 |
Valid |
|
GW-RS0820-11 |
5 Sep 2011 |
8
Sep 2011 to 7 Mar 2012 |
Expired |
|
Registration as a Chemical
Waste Producer |
WPN5213-147-C1169-35 |
15 Nov 2010 |
N/A |
Valid |
Water Discharge Licence |
WT00008780-2011 |
22 Mar 2011 |
22 Mar 2011 to 31 Mar 2016 |
Valid |
|
WT00010482-2011 |
30 Sep 2011 |
30 Sep 2011 to 30 Sep 2013 |
Valid |
WT00011322-2011 |
15 Dec 2011 |
15 Dec 2011 to 31 Dec 2013 |
Valid |
|
WT00011718-2012 |
16 Jan 2012 |
16 Jan 2012 to 31 Jan
2014 |
Valid |
|
Billing Account under Waste Disposal Ordinance |
7011553 |
30 Sep 2010 |
27 Sep 2010 to 27 Jan 2016 |
Valid |
Billing Account under Waste Disposal Ordinance (Dumping by
Vessel) |
7011761 |
26 Jan 2011 |
1 Feb 2012 to 16 Apr 2012 |
Valid |
Dumping Permit (Type 1 ¡V |
EP/MD/12-112 |
20 Jan 2012 |
20 Jan 2012 to 19 Jul 2012 |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate
Sites) & Type 2 ¡V Confined Marine disposal) |
EP/MD/12-096 |
28 Dec 2011 |
1 Dec 2011 to 31 Jan 2012 |
Expired |
EP/MD/12-123 |
8 Feb
2012 |
15 Feb 2012 to 14 Mar 2012 |
Expired |
Table
3.9 Summary of submission status under
FEP-04/356/2009 Condition
EP Condition |
Submission |
Date of
Submission |
Condition 2.7 |
Amendment for Works Schedule
and Location Plans |
12 Nov 2010 |
Condition 2.8 |
Silt Curtain Deployment Plan
Rev 2 |
11 May 2011 |
Condition 2.9 |
Silt Screen Deployment Plan
Rev3 |
15 Jun 2011 |
Condition 2.18 |
Amendment for Proposal for the
Removal of Odorous Sediment and Slime |
2 Aug 2011 |
Condition 2.21 |
Landscape Plan |
18 Feb 2011 |
Amendment for Noise Management
Plan |
27 Jan 2011 |
3.1.9.
Implementation status of the recommended mitigation
measures during this reporting period is presented in Appendix
3.1.
Contract no. HK/2010/06 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass over MTR Tsuen Wan Line
3.1.10. Summary of
the current status on licences and/or permits on environmental protection
pertinent and submission for contract no. HK/2010/06 under EP-356/2009 are
shown in Table 3.10 and Table 3.11.
Table
3.10 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2010/06
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-05/356/2009 |
24 Mar 2011 |
N/A |
Valid |
Notification of Works Under APCO |
326344 |
18 Jan 2011 |
N/A |
Valid |
Construction Noise Permit (CNP) for piling equipment |
PP-RS0045-11 |
22 Dec 2011 |
12 Jan to 5 Jul 2012 |
Valid |
Construction Noise Permit (CNP)
for non-piling equipment |
GW-RS0879-11 |
22
Sept 2011 |
6 Oct
2011 to 5 Apr 2012 |
Valid |
GW-RS0034-12 |
17
Jan 2012 |
18
Jan to 12 Jul 2012 |
Valid |
|
Billing Account under Waste Disposal Ordinance |
7012338 |
16 Feb 2011 |
N/A |
Valid |
Registration as Chemical Waste Producer |
WPN5213-134-G2533-01 |
11 Feb 2011 |
N/A |
Valid |
Water Discharge Licence |
WT00010905-2011 |
4 November 2011 |
31 July 2016 |
Valid |
Dumping Permit (Type 1 ¡V |
EP/MD/12-122 |
9 Feb 12 |
12 Feb 2012 to 11 Aug 2012 |
Valid |
Table
3.11 Summary of
submission status under EP-356/2009 and FEP-05/356/2009 Condition
EP Condition |
Submission |
Date
of Submission |
Condition 2.6 |
Management Organization of Main Construction Companies |
24 October 2011 |
Condition
2.7 |
Works
Schedule and Location Plans |
11 March
2011 |
Condition
2.8 |
Revised
Silt Curtain Deployment Plan |
31 Aug 2011 |
Condition
2.9 |
Silt
Screen Deployment Plan |
11 April 2011 |
Condition
2.23 |
Noise
Management Plan |
11 March 2011 |
Contract no. HY/2009/19 ¡V Central- Wan Chai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link
3.1.11. Summary of
the current status on licences and/or permits on environmental protection
pertinent for contract no. HY/2009/19 is shown in Table 3.12.
Table 3.12 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/19
Permit / Licence / Notification /
Approval |
Reference No. |
Issued Date |
Valid Period / Application Status |
Further Environmental Permit |
FEP-07/364/2009/A |
25 Feb 2011 |
Granted |
Notification of Works Under APCO |
326160 |
24 Jan 2011 |
Notified |
Construction Noise
Permit (CNP) (For D-wall construction) |
GW-RS0180-12 |
22-Feb-12 |
26-Aug-12 |
Construction Noise
Permit (CNP) (For Bored pile construction at Portion III) |
GW-RS0286-12 |
23-Mar-12 |
26-Sep-12 |
Construction Noise
Permit (CNP) (For |
GW-RS0028-12 |
18-Jan-12 |
17-Jun-12 |
Discharge Licence (Land) |
WT00010093-2011 |
31 Aug 2011 |
30-Sept-16 |
Discharge Licence (Sea) |
WT00010865-2011 |
03 Nov 2011 |
30-Nov-16 |
Registration as a
Waste Producer |
7012306 |
21 Jan 2011 |
Registered |
C&D Waste Disposal |
7012306 |
10 Feb 2011 |
Registered |
Vessel Disposal |
7013285 |
21 July 2011 |
Registered |
Registration as Chemical Waste Producer |
5213-151-C3654-01 |
24 Mar 201112 |
Registered |
Noise Monitoring Stations
4.1.1.
The noise monitoring stations for the Project are
listed and shown in Table 4.1 and Figure 4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table 4.1 Noise
Monitoring Station
Station |
Description |
M1a |
Harbour
Road Sports Centre |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
M4b |
Victoria
Centre |
M5b |
|
M6 |
HK |
Real-time Noise Monitoring Stations
4.1.2.
The real-time noise monitoring stations for the
Project are listed and shown in Table 4.2 and Figure 4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table 4.2 Real Time Noise Monitoring Station
District |
Station |
Description |
Tin
Hau |
RTN1 |
FEHD Hong Kong Transport Section
Whitefield Depot |
North Point |
RTN2 |
Oil Street Community Liaison
Centre |
Noise Monitoring Parameters, Frequency and Duration
4.1.3.
The construction noise
level shall be measured in terms of the A-weighted equivalent continuous sound
pressure level (Leq). Leq (30 minutes) shall be used as
the monitoring parameter for the time period between 0700 and 1900 hours on
normal weekdays. For all other time periods, Leq (5 minutes) shall
be employed for comparison with the Noise Control Ordinance (NCO) criteria.
Supplementary information for data auditing, statistical results such as L10
and L90 shall also be obtained for reference.
4.1.4.
Noise monitoring shall be carried out at all the
designated monitoring stations. The monitoring frequency shall depend on the
scale of the construction activities. The following is an initial guide on the
regular monitoring frequency for each station on a weekly basis when noise
generating activities are underway:
¡P
one set of
measurements between 0700 and 1900 hours on normal weekdays.
4.1.5.
If construction works are extended to include works
during the hours of 1900 ¡V 0700 as well as public holidays and Sundays,
additional weekly impact monitoring shall be carried out during respective
restricted hours periods. Applicable permits under NCO shall be obtained by the
Contractor.
Monitoring Equipment
4.1.6.
As referred to in the Technical Memorandum ™ issued
under the NCO, sound level meters in compliance with the International
Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type
1) specifications shall be used for carrying out the noise monitoring.
Immediately prior to and following each noise measurement the accuracy of the
sound level meter shall be checked using an acoustic calibrator generating a
known sound pressure level at a known frequency. Measurements may be accepted
as valid only if the calibration level from before and after the noise
measurement agree to within 1.0 dB.
4.1.7.
Noise measurements shall not be made in fog, rain,
wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10 m/s.
The wind speed shall be checked with a portable wind speed meter capable of
measuring the wind speed in m/s.
Air Quality Monitoring Stations
4.2.1.
The air monitoring stations for the Project are
listed and shown in Table 4.3 and Figure 4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table
4.3 Air Monitoring Station
Station ID |
Monitoring Location |
Description |
CMA1b |
Oil Street Community Liaison Centre |
North
Point |
CMA2a |
|
|
CMA3a |
CWB PRE
Site Office * |
|
CMA4a |
Society for the Prevention of
Cruelty to Animals |
Wan Chai |
CMA5a |
Children Playgrounds opposite to |
Wan Chai |
CMA6a |
WDII PRE
Site Office * |
Wan Chai |
* Remarks:
As per the ENPC meeting in January 2011, the monitoring stations CMA3a - Future
CWB site office at Wanchai Waterfront Promenade and CMA6a - Future AECOM site
office at Work Area were renamed as remark.
Air Monitoring Parameters, Frequency and Duration
4.2.2.
One-hour and 24-hour TSP levels should be measured
to indicate the impacts of construction dust on air quality. The 24-hour TSP
levels shall be measured by following the standard high volume sampling method
as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part
50), Appendix B.
4.2.3.
All relevant data including temperature, pressure,
weather conditions, elapsed-time meter reading for the start and stop of the
sampler, identification and weight of the filter paper, and any other local
atmospheric factors affecting or affected by site conditions, etc., shall be
recorded down in detail.
4.2.4.
For regular impact monitoring, the sampling
frequency of at least once in every six-days, shall be strictly observed at all
the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring,
the sampling frequency of at least three times in every six-days should be
undertaken when the highest dust impact occurs.
Sampling Procedure and Monitoring Equipment
4.2.5.
High volume samplers (HVSs) in compliance with the
following specifications shall be used for carrying out the 1-hour and 24-hour
TSP monitoring:
¡P
0.6 - 1.7 m3 per
minute adjustable flow range;
¡P
equipped with a
timing / control device with +/- 5 minutes accuracy for 24 hours operation;
¡P
installed with
elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
¡P
capable of
providing a minimum exposed area of 406 cm2;
¡P
flow control
accuracy: +/- 2.5% deviation over 24-hour sampling period;
¡P
equipped with a
shelter to protect the filter and sampler;
¡P
incorporated
with an electronic mass flow rate controller or other equivalent devices;
¡P
equipped with a
flow recorder for continuous monitoring;
¡P
provided with a
peaked roof inlet;
¡P
incorporated
with a manometer;
¡P
able to hold and
seal the filter paper to the sampler housing at horizontal position;
¡P
easily
changeable filter; and
¡P
capable of
operating continuously for a 24-hour period.
4.2.6.
Initial calibration of dust monitoring equipment
shall be conducted upon installation and thereafter at bi-monthly intervals.
The transfer standard shall be traceable to the internationally recognized
primary standard and be calibrated annually. The concern parties such as IEC
shall properly document the calibration data for future reference. All the data
should be converted into standard temperature and pressure condition.
Laboratory Measurement / Analysis
4.2.7.
A clean laboratory with constant temperature and
humidity control, and equipped with necessary measuring and conditioning
instruments to handle the dust samples collected, shall be available for sample
analysis, and equipment calibration and maintenance. The laboratory should be
HOKLAS accredited.
4.2.8.
An alternative non-HOKLAS
accredited laboratory was set-up for carrying out
the laboratory analysis, the laboratory equipment was approved by the ER
on 8 February 2011 and the measurement procedures were witnessed by the IEC. Any measurement performed by the laboratory was be demonstrated to the satisfaction of the ER and IEC. IEC shall
regularly audit to the measurement performed by the laboratory to ensure the
accuracy of measurement results.
4.2.9.
Filter paper of size 8" x 10" shall be
labelled before sampling. It shall be a clean filter paper with no pinholes,
and shall be conditioned in a humidity-controlled chamber for over 24-hours and
be pre-weighed before use for the sampling.
4.2.10. After
sampling, the filter paper loaded with dust shall be kept in a clean and
tightly sealed plastic bag. The filter paper shall then be returned to the
laboratory for reconditioning in the humidity controlled chamber followed by
accurate weighing by an electronic balance with readout down to 0.1 mg. The
balance shall be regularly calibrated against a traceable standard.
4.2.11. All the
collected samples shall be kept in a good condition for 6 months before
disposal.
impact monitoring for odour patrol
4.2.12. Odour
patrols along the shorelines of Causeway Bay Typhoon Shelter and ex-Wan Chai
Public Cargo Working Area when there is temporary reclamation in Causeway Bay
Typhoon Shelter and/or in the ex-Wan Chai Public Cargo Working Area, or when
there is dredging of the odorous sediment and slime at the south-western corner
of the Causeway Bay Typhoon Shelter. Odour patrols will be carried out at
bi-weekly intervals during July, August and September by a qualified person of
the ET who shall:
¡P
be at least 16
years of age;
¡P
be free from any
respiratory illnesses; and
¡P
not be allowed
to smoke, eat, drink (except water) or use chewing gum or sweets 30 min
¡P
before and
during odour patrol
4.2.13. Odour
patrol shall be conducted by independent trained personnel / competent persons
patrolling and sniffing around the shore as shown in Figure 4.1 to detect any odour at
the concerned hours (afternoon is preferred for higher daily temperature).
4.2.14. The
qualified person will use the nose (olfactory sensor) to sniff odours at
different locations. The main odour emission sources and the areas to be
affected by the odour nuisance will be identified.
4.2.15. The
perceived odour intensity is to be divided into 5 levels which are ranked in
the descending order as follows:
¡P
0 - Not
detected. No odour perceived or an odour so weak that it cannot be easily characterized
or described;
¡P
1 - Slight
Identifiable odour, and slight chance to have odour nuisance;
¡P
2 - Moderate
Identifiable odour, and moderate chance to have odour nuisance;
¡P
3 - Strong
Identifiable, likely to have odour nuisance;
¡P
4 - Extreme
Severe odour, and unacceptable odour level.
4.2.16.
The findings including odour intensity, odour
nature and possible odour sources, and also the local wind speed and direction
at each location will be recorded. In addition, some relevant meteorological
and tidal data such as daily average temperature, and daily average humidity,
on that surveyed day will be obtained from the Hong Kong Observatory Station
for reference. The Action and Limit levels for odour patrol are shown in Appendix 6.1.
4.2.17.
The qualified odour patrol member has individual
n-butanol thresholds complied with the requirement of European Standard Method
of Air Quality ¡V Determination of Odour Concentration by Dynamic Olfactometry
(EN13725) in the range of 20 to 80 ppb. The certificate for the qualified odour
panel member is shown in Appendix 4.2.
4.3.1.
The EIA Report has identified that the key water
quality impact would be associated with the dredging works during the
construction phase. Marine water quality monitoring for dissolved oxygen (DO),
suspended solid (SS) and turbidity is therefore recommended to be carried out
at selected WSD flushing water intakes. The impact monitoring should be carried
out during the proposed dredging works to ensure the compliance with the water
quality standards.
4.3.2.
The updated EM&A Manual for EP-356/2009
(Version in March 2011) is approval by EPD on 29 April 2011. As such, the
Action Level and Limit Level for the wet season (April ¡V September) will be
effected and applied to the water quality monitoring data from 30 April 2011.
Water Quality Monitoring Stations
4.3.3.
It is proposed to monitor the water quality at 9
WSD salt water intakes and 14 cooling water intakes along the seafront of the
Table 4.4 Marine
Water Quality Stations for Water Quality Monitoring
Station Ref. |
Location |
Easting |
Northing |
WSD Salt
Water Intake |
|||
WSD7 |
|
834150.0 |
818300.3 |
WSD9 |
Tai Wan |
837921.0 |
818330.0 |
WSD10 |
Cha Kwo Ling |
841900.9 |
817700.1 |
WSD15 |
Sai Wan Ho |
841110.4 |
816450.1 |
WSD17 |
|
839790.3 |
817032.2 |
WSD19 |
Sheung Wan |
833415.0 |
816771.0 |
WSD20 |
|
830750.6 |
816030.3 |
WSD21 |
Wan Chai |
836220.8 |
815940.1 |
RW1 |
Wan Chai (Reprovision) |
836188.8 |
815911.1 |
Cooling
Water Intake |
|||
C1 |
HKCEC Extension |
835885.6 |
816223.0 |
C2 |
Telecom House |
835647.9 |
815864.4 |
C3 |
HKCEC Phase I |
835836.2 |
815910.0 |
C4e |
Great Eagle Centre |
835932.8 |
815888.2 |
C4w |
Wan |
835629.8 |
815889.2 |
C5e |
Sun Hung Kai Centre (Eastern) |
836250.1 |
815932.2 |
C5w |
Sun Hung Kai Centre (Western) |
836248.1 |
815933.2 |
C6 |
Excelsior
Hotel |
837009.6 |
815999.3 |
C7 |
|
837193.7 |
816150.0 |
C8 |
|
837970.6 |
816957.3 |
C9 |
Provident Garden |
838355.0 |
817116.6 |
RC1 |
Proposed
HKAPA Extension |
835487.7 |
815987.7 |
RC5 |
Sun Hung
Kai Centre (Reprovision) |
836291.4 |
816029.7 |
RC7 |
|
837245.2 |
816156.6 |
Water Quality Parameters
4.3.4.
Monitoring of dissolved oxygen (DO), turbidity and
suspended solids (SS) shall be carried out at WSD flushing water intakes and
cooling water intakes. DO and Turbidity are measured in-situ while SS is
determined in laboratory.
4.3.5.
In association with the water quality parameters,
other relevant data shall also be measured, such as monitoring
location/position, time, sampling depth, water temperature, pH, salinity,
dissolved oxygen (DO) saturation, weather conditions, sea conditions, tidal
stage, and any special phenomena and work underway at the construction site
etc.
Sampling Procedures and Monitoring Equipment
4.3.6.
The interval between two sets of monitoring should
not be less than 36 hours except where there are exceedances of Action and/or
Limit Levels, in which case the monitoring frequency will be increased. Table
4.5 shows the proposed monitoring frequency and water quality
parameters. Duplicate in-situ measurements and water sampling should be carried
out in each sampling event. For selection of tides for in-situ measurement and
water sampling, tidal range of individual flood and ebb tides should be not
less than 0.5m.
Table 4.5 Marine
Water Quality Monitoring Frequency and Parameters
Activities |
Monitoring Frequency1 |
Parameters2 |
During the 4-week baseline
monitoring period |
Three days per week, at mid-flood
and mid-ebb tides |
Turbidity, Suspended Solids (SS),
Dissolved Oxygen (DO), pH, Temperature, Salinity |
During marine
construction works |
Three days per week, at mid-flood and
mid-ebb tides |
Turbidity, Suspended Solids (SS),
Dissolved Oxygen (DO), pH, Temperature, Salinity |
After
completion of marine construction works |
Three days per week, at mid-flood
and mid-ebb tides |
Turbidity, Suspended Solids (SS),
Dissolved Oxygen (DO), pH, Temperature, Salinity |
Notes:
1.
For selection of tides for in-situ measurement and water
sampling, tidal range of individual flood and ebb tides should be not less than
0.5m.
2.
Turbidity should be measured in situ whereas SS should be
determined by laboratory.
Dissolved Oxygen and Temperature Measuring
Equipment
4.3.7.
The instrument should be a portable, weatherproof
dissolved oxygen measuring instrument complete with cable, sensor,
comprehensive operation manuals, and use a DC power source. It should be
capable of measuring:
¡P
a dissolved
oxygen level in the range of 0-20 mg/l and 0-200% saturation
¡P
a temperature of
0-45 degree Celsius
4.3.8.
It should have a membrane electrode with automatic
temperature compensation complete with a cable. Sufficient stocks of spare
electrodes and cables should be available for replacement where necessary.
(e.g. YSI model 59 meter, YSI 5739 probe, YSI 5795A submersible stirrer with
reel and cable or an approved similar instrument).
4.3.9.
Should salinity compensation not be build-in in the
DO equipment, in-situ salinity shall be measured to calibrate the DO equipment
prior to each DO measurement.
Turbidity Measurement Instrument
4.3.10. The
instrument should be a portable, weatherproof turbidity-measuring instrument
complete with comprehensive operation manual. The equipment should use a DC
power source. It should have a photoelectric sensor capable of measuring
turbidity between 0‑1000 NTU and be complete with a cable (e.g. Hach model
2100P or an approved similar instrument).
Sampler
4.3.11. A water
sampler comprises a transparent PVC cylinder, with a capacity of not less than
2 litres, and can be effectively sealed with latex cups at both ends. The
sampler should have a positive latching system to keep it open and prevent
premature closure until released by a messenger when the sampler is at the
selected water depth (e.g. Kahlsico Water Sampler or an approved similar
instrument).
Sample Container and Storage
4.3.12. Water
samples for suspended solids measurement should be collected in high-density
polythene bottles, packed in ice (cooled to 4¢XC without being frozen), and
delivered to ALS Technichem (HK) Pty Ltd. as soon as possible after collection
for analysis.
Water Depth Detector
4.3.13. A
portable, battery-operated echo sounder shall be used for the determination of
water depth at each designated monitoring station. This unit can either be
handheld or affixed to the bottom of the workboat, if the same vessel is to be
used throughout the monitoring programme.
Salinity
4.3.14. A portable
salinometer capable of measuring salinity in the range of 0-40 ppt shall be
provided for measuring salinity of the water at each of monitoring location.
Monitoring Position Equipment
4.3.15. A
hand-held or boat-fixed type digital Global Positioning System (GPS) with
waypoint bearing indication or other equivalent instrument of similar accuracy
shall be provided and used during monitoring to ensure the monitoring vessel is
at the correct location before taking measurements.
Calibration of In-situ Instruments
4.3.16. All
in-situ monitoring instrument shall be checked, calibrated and certified by a
laboratory accredited under HOKLAS or equivalent before use, and subsequently
re-calibrated at 3 monthly intervals throughout all stages of the water quality
monitoring. Responses of sensors and electrodes should be checked with certified
standard solutions before each use. Wet bulb calibration for a DO meter shall
be carried out before measurement at each monitoring location.
4.3.17. For the on
site calibration of field equipment by the ET, the BS 127:1993, "Guide to
Field and on-site test methods for the analysis of waters" should be
observed.
4.3.18. Sufficient
stocks of spare parts should be maintained for replacements when necessary.
Backup monitoring equipment shall also be made available so that monitoring can
proceed uninterrupted even when some equipment is under maintenance,
calibration, etc.
4.3.19. Current
calibration certificates of equipments are presented in Appendix 4.2.
Laboratory Measurement / Analysis
4.3.20. Analysis
of suspended solids has been carried out in a HOKLAS accredited laboratory, ALS
Technichem (HK) Pty Ltd. Water samples of about 1L shall be collected at the
monitoring stations for carrying out the laboratory SS determination. The SS
determination work shall start within 24 hours after collection of the water
samples. The SS determination shall follow APHA 19ed or equivalent methods
subject to the approval of IEC and EPD.
Enhanced Water Quality
Monitoring in the ex-Wan Chai Public Cargo
Working Area and the
4.3.21. The
enhanced water quality monitoring and audit programme is to avoid aggravation
of odour nuisance from seawater arising from temporary reclamation in the
ex-Wan Chai Public Cargo Working Area and the Causeway Bay Typhoon Shelter.
4.3.22. Dissolved oxygen
monitoring at the intakes C6 and C7 in Causeway Bay Typhoon Shelter when there
is temporary reclamation in Causeway Bay Typhoon Shelter and at the
south-western and south-eastern corners of the ex-Wan Chai Public Cargo Working
Area. The proposed water quality monitoring stations of the Project are shown
in Table 4.6 and Figure 4.1.
Table
4.6 Marine Water
Quality Stations for Enhanced Water Quality Monitoring
Station |
Location |
C6 |
Excelsior
Hotel |
C7 |
|
Ex-WPCWA-SW |
South-western
of the ex-Wan Chai Public Cargo Working Area |
Ex-WPCWA-SE |
South-eastern
of the ex-Wan Chai Public Cargo Working Area |
4.3.23. The
monitoring of dissolved oxygen are to be carried out 3 days per week, at
mid-flood and mid-ebb tides for 3 water depths (1m below water surface,
mid-depth and 1m above sea bed, except where the water depth less than 6m, the
mid-depth may be omitted. If the water depth be equal to or less than 3m, only
the mid-depth will be monitored).
Daily SS Monitoring and 24
hours Turbidity Monitoring System
4.3.24.
During dredging of the sediment at the
south-western corner of the Causeway Bay Typhoon Shelter, daily monitoring of
suspended solids and 24 hour monitoring of turbidity at the cooling water
intakes (C6 and C7) shall be conducted.
4.3.25.
The 24 hours monitoring of turbidty at the cooling water
intakes (C6 and C7) shall be established by setting up a continuous water quality
monitoring station in front of the intakes during the dredging activities. The
monitoring system include the turbidity sensor and data logger which is capable
of data capturing at every 5 minutes. The data sahll be downloaded daily and
compared with the Action and Limit level determined during the baseline water qualtiy
monitoring at the cooling water intake locations.
Additional Dissovled
oxygen Monitoring FOR CULVERT L WATER DISCHARGE FLOW
4.3.26.
In
response to the Condition 2.18 of the Environmental Permit no. EP-356/2009
requiring that a silt curtain / impermeable barrier system be installed to
channel water discharge flow from Culvert L to locations outside the embayment
area, a proposed replacement of the requirement with additional dissolved
oxygen monitoring has been conducted at three monitoring stations, namely A, B
and C between the eastern seawall of Central Reclamation Phase III and the
HKCEC Extension since November 2011 under EP-356/2009 so that DO level between
the eastern seawall of Central Reclamation Phase II and the HKCEC extension
could be continuously monitored.
4.3.27. The
proposed DO monitoring stations of the Project are shown in Table 4.7 and
Figure 4.1.
Table
4.7 Marine Water
Quality Stations for Additional DO Monitoring
Station |
Easting |
Northing |
A |
835468 |
815857 |
B |
835572 |
815961 |
C |
835659 |
816271 |
4.3.28.
The monitoring of dissolved oxygen are to be
carried out once per week, at mid-flood and mid-ebb tides for 3 water depths
(1m below water surface, mid-depth and 1m above sea bed, except where the water
depth less than 6m, the mid-depth may be omitted. If the water depth be equal
to or less than 3m, only the mid-depth will be monitored).
5.0.1.
The environmental monitoring will be implemented
based on the division of works areas of each designed project managed under
different contracts with separate FEP applied by individual contractors.
Overall layout showing work areas of various contracts, latest status of work
commencement and monitoring stations is shown in Figure 2.1 and Figure 4.1. The monitoring results
are presented in according to the Individual Contract(s).
5.0.2.
The major work activities for Contract no.
HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The
construction site was handed over to contractor HY/2009/19 on 31
December 2011.
5.0.3.
The surrender of the Further Environmental Permit
for HY/2009/11 withdrew by contractor on 14 February 2012. However, there is no
work was conducted by the contractor.
5.0.4.
In the reporting month, the concurrent contracts
are as follows:
Contract no. HY/2009/11 Central - Wan Chai Bypass - North Point
Reclamation;
Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central-Wan
Chai Bypass at
Contract no. HK/2009/02 Wan Chai Development Phase II ¡V Central-Wan Chai
Bypass at Wan Chai East
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (
Contract no. HK/2010/06 Wan Chai Development Phase II ¡V Central-Wan Chai
Bypass over MTR Tsuen Wan Line
Contract no. HY/2009/19- Cental- Wan Chai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link
5.0.5.
The environment monitoring schedules for reporting
month and coming month are presented in Appendix 5.1.
Contract no. HY/2009/11 ¡V Central
¡V Wanchai Bypass, North Point Reclamation
5.1.1.
The major work activities for Contract no.
HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The
construction site was handed over to contractor HY/2009/19 on 31 December 2011
and the FEP-01/356/2009 was under application of surrender in this reporting
period. The monitoring was temporary suspended since 5 January 2012.
5.1.2.
The proposed division of noise monitoring stations
for Contract no. HY/2009/11 are summarized in Table 5.1 below:
Table 5.1 Noise
Monitoring Stations for Contract no. HY/2009/11
Station |
Description |
M4b |
Victoria Centre |
M5b |
|
5.1.3.
Day time and evening period noise monitoring was
conducted at the
5.1.4.
Noise monitoring results measured in this reporting
period are reviewed and summarized. No exceedance was recorded in reporting
month. Details of noise monitoring results and graphical presentation can be
referred in Appendix 5.2.
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC, Contract no. HK/2009/02 - Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East and Contract
no. HK/2010/06 Wan Chai Development Phase II ¡V Central-Wan Chai Bypass over MTR
Tsuen Wan Line
5.1.5.
The proposed division of noise monitoring stations
are summarized in Table 5.2 below.
Table 5.2 Noise
Monitoring Station for Contract nos. HK/2009/01, HK/2009/02 and HK/2010/06
Station |
Description |
M1a |
Harbour Road Sports Centre |
5.1.6.
Daytime and evening period noise monitoring was
conducted at the Harbour Road Sport Centre in the reporting month.
Contract
no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (
5.1.7.
The noise monitoring for HY/2009/15 was commenced
on 10 November 2010. The proposed division of noise monitoring stations are
summarized in Table 5.3 below.
Table 5.3 Noise Monitoring Station for Contract no. HY/2009/15
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
5.1.8.
Noise monitoring results measured in the period of
daytime and restricted hour are reviewed and summarized. No exceedance was
recorded in reporting month. Details of noise monitoring results and graphical
presentation can be referred in Appendix 5.2.
Contract no. HY/2009/19- Wan Chai Bypass Tunnal
(North Point Section) and Island Eastern Corridor Link
5.1.9.
The proposed division of noise monitoring stations
are summarized in Table 5.4 below.
Table 5.4 Noise Monitoring Station for Contract no. HY/2009/19
Station |
Description |
M3a |
Tung Lo
Wan Fire Station |
M4b |
Victoria
Centre |
M5b |
|
M6 |
HK |
No action level exceedance and
three limit level exceedances were recorded on 28 February, 13 and 27 March
2012 at M6 ¡V HK Baptist Church Henrietta Secondary School in the reporting
month. Major traffic jam and no major work activities were observed during
monitoring, the exceedances were considered as non-project related.
Contract no. HY/2009/11 ¡V Central ¡V Wanchai Bypass,
North Point Reclamation
5.2.1.
The major work activities for Contract no.
HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The
construction site was handed over to contractor HY/2009/19 on 31
December 2011 and the FEP-01/356/2009 was under application of surrender in
this reporting period. The monitoring was temporary suspended since 5 January
2012.
Table 5.5 Real
Time Noise Monitoring Station for Contract no. HY/2009/11 and HY/2009/19
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong
Transport Section Whitefield
Depot |
North Point |
RTN2 |
Oil Street
Community Liaison Centre |
* Real time noise
monitoring results and graphical presentation during night time period are for
information only.
5.2.2.
Real time noise monitoring results were reviewed
and no project-related Action and Limit level exceedance were recorded in the
reporting period. Details of real time noise monitoring results and graphical
presentation can be referred to Appendix 5.5.
5.3.1.
Due to lack of electricity supply, the 24-hr TSP
monitoring at the following stations were rescheduled:
CMA1b: from 13 Mar 2012 to 14 Mar 2012
CMA3a: from 24 Mar 2012 to 26 Mar 2012
Contract no. HY/2009/11 ¡V Central ¡V Wanchai Bypass,
North Point Reclamation
5.3.2.
The major work activities for Contract no.
HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The
construction site was handed over to contractor HY/2009/19 on 31 December 2011and
the FEP-01/356/2009 was valid in this reporting period. The monitoring for the
contract was temporary suspended on 6 January 2012.
5.3.3.
The proposed division air monitoring stations is
summarized in Table 5.6 below.
Table 5.6 Air
Monitoring Stations for Contract no. HY/2009/11
Station |
Description |
CMA1b |
Oil Street Community Liaison Centre |
CMA2a |
|
5.3.4.
No exceedance was recorded in the reporting month.
Details of air monitoring results and graphical presentation can be referred in
Appendix 5.3.
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
5.3.5.
Air monitoring was commenced on 1 April 2011 in
response to the commencement of the land-filling work for Contract no.
HK/2009/01. The proposed division of air monitoring stations are summarized in Table
5.7 below. No exceedance was recorded in the reporting month.
Table 5.7 Air
Monitoring Stations for Contract no. HK/2009/01
Station |
Description |
CMA5a |
Children Playgrounds opposite to |
CMA6a |
WDII PRE Site Office |
Contract no. HK/2009/02 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
5.3.6.
Air monitoring was commenced in mid-January 2011
for the land-filling work for Contract no. HK/2009/02. The proposed division of
air monitoring stations are summarized in Table 5.8 below. No
exceedance was recorded in the reporting month.
Table 5.8 Air
Monitoring Station for Contract no. HK/2009/02
Station |
Description |
CMA4a |
Society for the Prevention of Cruelty to Animals |
Contract no.
HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (
5.3.7.
Air monitoring was commenced on 15 March 2011 for
the land filling work for Contract no. HY/2009/15. The proposed division of air
monitoring stations are summarized in Table 5.9 below. No
exceedance was recorded in the reporting month.
Table
5.9 Air
Monitoring Station for Contract no. HY/2009/15
Station |
Description |
CMA3a |
CWB PRE Site Office |
Contract no.
HY/2009/19- Wan Chai Bypass Tunnal (North Point Section) and Island Eastern
Corridor Link
5.3.8.
The proposed division of air monitoring stations
are summarized in Table 5.10 below. Air monitoring for the tunnel works under
contract no. HY/2009/19 was commenced on 26 April 2011. No exceedance was
recorded in the reporting month.
Table 5.10 Air Monitoring Stations for Contract no.
HY/2009/19
Station |
Description |
CMA1b |
Oil St Community Liaison Centre |
CMA2a |
|
5.4.1.
WDII/RSS
advised that the dredging works for submarine pipeline at
5.4.2.
Based
on the joint inspection on 4 Jan 2012 for the NPR area, the 4-week water
quality monitoring at WSD9, WSD10, WSD15, WSD17, C8, C9 to confirm no water
deterioration with respect to NPR was commenced since 7 Jan 2012 and it was
completed on 6 February 2012.
5.4.3.
Water
quality monitoring at WSD10 and WSD15 was temporary suspended while water
quality monitoring at WSD9 and WSD17 was implemented with respect to HK/2009/02
from 8 Feb 12 onwards;
5.4.4.
Water
quality monitoring at C8 and C9 have been implemented with respect to
HY/2009/19 since the marine bore piling work started on 28 Jan 12.
5.4.5.
Based
on the safety concern when external façade refurbishment was conducted by
contractor employed by Provident Center (C9) since 3 Feb 2012, there is a fine
adjustment of the sampling location of water quality monitoring at C9 to the
closest accessible point prior to the completion of the external façade
refurbishment work.
5.4.6.
With respect to the trial
dredging at WCR2 was scheduled on 20, 22, 24, 25 March and 1, 3 Apr 2012,
on-going water quality monitoring results at WSD21 during this period was
checked and indicated that there was no contribution due to the trial dredging
operation. Enhanced review of water quality around WCR2 was also
implemented and no deterioration in the water quality was observed.
Contract no. HY/2009/11 ¡V Central ¡V Wanchai Bypass,
North Point Reclamation
5.4.7.
The major work activities for Contract no.
HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The
construction site was handed over to contractor HY/2009/19 on 31
December 2011 and the FEP-01/356/2009 was valid in this reporting period.
5.4.8.
The proposed division of water monitoring stations
for Contract no. HY/2009/11 are summarized in Table 5.11 below:
Table 5.11 Water Monitoring Stations for Contract no. HY/2009/11
Station Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD9 |
Tai Wan |
837921.0 |
818330.0 |
WSD10 |
Cha Kwo Ling |
841900.9 |
817700.1 |
WSD15 |
Sai Wan Ho |
841110.4 |
816450.1 |
WSD17 |
|
839790.3 |
817032.2 |
Cooling Water Intake |
|||
C8 |
|
837970.6 |
816957.3 |
C9 |
Provident Garden |
838355.0 |
817116.6 |
Remarks: WSD9,
WSD10, WSD15, WSD17, C8 and C9 water monitoring finished on 6 Feb 2012.
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
5.4.9.
Water monitoring for Contract no. HK/2009/01 was
commenced on 23 July 2010. The proposed division of water monitoring stations
are summarized in Table 5.12 below.
Table 5.12 Water
Monitoring Stations for Contract no. HK/2009/01
Station Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD7 |
|
834150.0 |
818300.3 |
WSD19 |
Sheung Wan |
833415.0 |
816771.0 |
WSD20 |
|
830750.6 |
816030.3 |
Cooling Water Intake |
|||
C1 |
HKCEC Extension |
835885.6 |
816223.0 |
C2 |
Telecom House |
835647.9 |
815864.4 |
C3 |
HKCEC Phase I |
835836.2 |
815910.0 |
C4e |
Great Eagle Centre |
835932.8 |
815888.2 |
C4w |
Wan |
835629.8 |
815889.2 |
Remarks:
The water
monitoring stations for the dredging works under Contract No. HK/2009/01 should
also include WSD9, WSD17, WSD 21 and C5 if water quality monitoring at these
locations have not been carried out by others. Similarly, the water monitoring
stations for the dredging works under Contract No. HK/2009/02 should also
include WSD7, WSD9, WSD17, WSD 19, C1, C2, C3 and C4 if water quality
monitoring at these locations have not been carried out by others.
Contract no. HK/2009/02 - Wan Chai Development Wan
Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
5.4.10.
Water monitoring for Contract no. HK/2009/02 was
commenced on 8 July 2010. The proposed division of water monitoring stations
are summarized in Table 5.13 below.
Table 5.13 Water
Monitoring Stations for Contract no. HK/2009/02
Station Ref. |
Location |
Easting |
Northing |
|||
WSD Salt Water Intake |
||||||
WSD21 |
Wan Chai |
836220.8 |
815940.1 |
|||
WSD9 (Monitoring started from 8 Feb 12) |
Sheung Wan |
833415.0 |
816771.0 |
|||
WSD17 (Monitoring started from 8 Feb 12) |
|
830750.6 |
816030.3 |
|||
Cooling Water Intake |
||||||
C5e |
Sun Hung Kai Centre (Eastern) |
836250.1 |
815932.2 |
|||
C5w |
Sun Hung Kai Centre (Western) |
836248.1 |
815933.2 |
|||
Remarks:
-
The water
monitoring stations for the dredging works under Contract No. HK/2009/01 should
also include WSD9, WSD17, WSD 21 and C5 if water quality monitoring at these
locations have not been carried out by others. Similarly, the water monitoring
stations for the dredging works under Contract No. HK/2009/02 should also
include WSD7, WSD9, WSD17, WSD 19, C1, C2, C3 and C4 if water quality
monitoring at these locations has not been carried out by others.
-
Water quality
monitoring at WSD9 and WSD 17 was implemented with respect to HK/2009/02 from 8
Feb 2012.
Contract
no. HK/2010/06 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass over
MTR Tsuen Wan Line
5.4.11.
Water monitoring for Contract no. HK/2010/06 was
commenced on 8 March 2011. The proposed division of water monitoring stations
are summarized in Table 5.14 below.
Table 5.14 Water
Monitoring Stations for Contract no. HK/2010/06
Station Ref. |
Location |
Easting |
Northing |
Cooling Water Intake |
|||
C2 |
Telecom House |
835647.9 |
815864.4 |
Contract no.
HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (
5.4.12.
Due to the commencement of the maintenance dredging
on 10 November 2010, water quality monitoring for Contract no. HY/2009/15 was
commenced on 9 November 2010. The proposed division of water monitoring
stations are summarized in Table 5.15 below.
Table 5.15 Water
Monitoring Stations for Contract no. HY/2009/15
Station Ref. |
Location |
Easting |
Northing |
Cooling Water Intake |
|||
C6 |
Excelsior Hotel |
837009.6 |
815999.3 |
C7 |
|
837193.7 |
816150.0 |
Remarks: - The cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated since 17 May 2011.
Contract no. HY/2009/19 ¡V Central- Wan Chai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link
5.4.13.
Due to the commencement of the marine bored piling
on 28 Jan 2012, water quality monitoring for Contract no. HY/2009/19 was
commenced on 28 Jan 2012. The proposed division of water monitoring stations
are summarized in Table 5.16 below.
Table 5.16 Water
Monitoring Stations for Contract no. HY/2009/19
Station Ref. |
Location |
Easting |
Northing |
Cooling Water Intake |
|||
C8 |
|
837970.6 |
816957.3 |
C9 |
Provident
Garden |
838355.0 |
817116.6 |
Remarks: C8 and C9 monitoring commenced on 28 Jan 2012.
5.4.14. Based on the safety concern when
external façade refurbishment was conducted by contractor employed by Provident
Center (C9) between 9 January 2012 to 30 July 2012 which caused to the
inaccessibility of sampling either land and marine since 3 Feb 2012, there is a
fine adjustment of the sampling location of water quality monitoring at C9
since 10 March 2012 to the closest accessible point prior to the completion of
the external façade refurbishment work.
5.4.15. As per the meeting with the
representative of Excelsior Hotel and World Trade Centre on 17 May 2011, they
confirmed that the seawater intake for The Excelsior was no longer in use and
replaced by the connected permanent water supply from WSD pipelines since 11
January 2011. Thus, the impact water quality monitoring for the cooling intake
- C6 was terminated effective from 26 May 2011.
5.4.16. 24 hours monitoring of turbidity at the cooling water intakes
at C7 was conducted. With respect to the seawall collapsing
at TS4 on 17 November 2011, the 24 hours turbidity monitoring and was kept in
November 2011. Since the
reinstating the seawall was completed on 13 January 2012 and no any water deterioration
was performed, 24 hour turbidity monitoring was then suspended on 27 January
2012.
5.4.17.
Water monitoring results measured in this reporting
period are reviewed and summarized. Details of water quality monitoring results and
graphical presentation can be referred in Appendix 5.4.
Table 5.17 Summary
of Water Quality Monitoring Exceedances in Reporting Month
Contract no. |
Water Monitoring Station |
Mid-flood |
Mid-ebb |
|||||||||||
DO |
Turbidity |
SS |
DO |
Turbidity |
SS |
|||||||||
|
LL |
|
LL |
|
LL |
|
LL |
|
LL |
|
LL |
|||
HY/2009/11 |
WSD9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Monitoring finished on 6 Feb 2012 |
WSD10 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
WSD15 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
WSD17 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C8 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HK/2009/01 |
WSD19 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
1 |
|
|
WSD20 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
|
|
WSD7 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C3 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C4e |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C4w |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HK/2009/01 &
HK/2010/06 |
C2 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HK/2009/02 |
C5e |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C5w |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
WSD21 |
0 |
0 |
1 |
1 |
0 |
1 |
0 |
0 |
2 |
1 |
1 |
0 |
|
Monitoring started on 8 Feb 2012 |
WSD9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Monitoring started on 8 Feb 2012 |
WSD17 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
1 |
0 |
1 |
|
HY/2009/15 |
C7 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
|
HY/2009/19 Monitoring
started on 28 Jan 2012 |
C8 |
0 |
0 |
1 |
1 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
|
C9 |
0 |
0 |
0 |
3 |
3 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
||
Total |
0 |
0 |
3 |
5 |
7 |
3 |
0 |
0 |
3 |
4 |
1 |
2 |
||
Remarks: - The cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated since 17 May 2011.
- WSD9 and WSD17 were implemented with respect to HK/2009/02 from 8 Feb 2012.
-
4-week water quality monitoring at WSD9, WSD10, WSD15, WSD17, C8, C9
were completed on 6 Feb 2012.
- C8 and C9 were implemented with
respect to HY/2009/19 from 28 Jan 2012.
5.4.18. Enhanced DO monitoring at 4
monitoring stations in Causeway Bay Typhoon Shelter and Ex-Public Cargo Works
Area was conducted three days per week during the reporting period. The action
and limit level exceedances of water quality monitoring are summarized in Table 5.18.
Table 5.18 Summary
of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month
Contract no. |
Water Monitoring Station |
Mid-flood |
Mid-ebb |
||
DO |
DO |
||||
|
LL |
|
LL |
||
C6 |
0 |
0 |
0 |
0 |
|
C7 |
0 |
0 |
0 |
0 |
|
Ex-WPCWA SW |
0 |
0 |
0 |
0 |
|
Ex-WPCWA SE |
0 |
0 |
0 |
0 |
|
Total |
0 |
0 |
0 |
0 |
5.4.19.
There is no exceedance in enhanced dissolved oxygen
monitoring in this reporting period.
5.4.20. In response to the Condition 2.18
of the Environmental Permit no. EP-356/2009 requiring that a silt curtain /
impermeable barrier system be installed to channel water discharge flow from
Culvert L to locations outside the embayment area, a proposed replacement of
the requirement with additional dissolved oxygen monitoring has been conducted
at three monitoring stations, namely A, B and C between the eastern seawall of
Central Reclamation Phase III and the HKCEC Extension since November 2011 under
EP-356/2009 so that DO level between the eastern seawall of Central Reclamation
Phase II and the HKCEC extension could be continuously monitored. Details of additional DO monitoring results can be
referred in Appendix
5.4a.
Contract no. HY/2009/11 ¡V Central ¡V Wanchai Bypass,
North Point Reclamation
5.5.1.
The major work activities for Contract no.
HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012.
Therefore, no C&D waste was generated.
Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central
¡VWanchai Bypass at HKCEC
5.5.2.
Inert and non- inert C&D waste were disposed of
in this reporting month. Details of the waste flow table are summarized in Table
5.19.
Table 5.19 Details of Waste Disposal for Contract no. HK/2009/01
Waste
Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert
C&D materials disposed, m3 |
2904.12 |
19438.28 |
TKO137, TM38 |
Inert
C&D materials recycled, m3 |
0 |
389.96 |
N/A |
Non-inert
C&D materials disposed, m3 |
37.24 |
651.44 |
|
Non-inert
C&D materials recycled, kg |
3560 |
139314 |
N/A |
Chemical
waste disposed, kg |
200 |
5860 |
N/A |
*Marine
Sediment (Type 1 ¡V Open Sea Disposal), m3 |
0 (Bulk Volume) |
83,482.2 (Bulk Volume) |
South of Cheung Chau |
* Marine
Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites)
& Type 2 ¡V Confined Marine Disposal) , m3 |
3411 Bulk Volume) |
26797 (Bulk Volume) |
East of Cha Chau |
Dredged Sediment Requiring Type 3 ¡V Special Treatment / Disposal
contained in Geosynthetic Containers |
1696 (Bulk Volume) |
5613 (Bulk Volume) |
East of Cha Chau |
5.5.3.
There were marine sediments Type 1 ¡V Open Sea Disposal
(Dedicate Sites) & Type 2 ¡V Confined Marine Disposal and Type 3 ¡V Special Treatment / Disposal
contained in Geosynthetic Containers disposed in the reporting month. The
maximum dredging rate in cross harbour water main is 533 m3 per day,
which is complied with the recommended maximum dredging rate listed in Table 2
of FEP-02/356/2009.
Contract no. HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass at WanChai East
5.5.4.
Inert and non- inert C&D waste were disposed of
in this reporting month. Details of the waste flow table are summarized in Table
5.20.
Table
5.20 Details of
Waste Disposal for Contract no. HK/2009/02
Waste
Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert
C&D materials disposed, m3 |
23,629 |
107,694 |
TKO137 / TM 38 |
Inert
C&D materials recycled, m3 |
NIL |
NIL |
N/A |
Non-inert
C&D materials disposed, m3 |
35 |
384 |
SENT Landfill |
Non-inert
C&D materials recycled, m3 |
NIL |
NIL |
N/A |
Chemical
waste disposed, kg |
Nil |
4,186 |
N/A |
Marine
Sediment (Type 1 ¡V Open Sea Disposal), m3 |
NIL |
154,827 (Bulk volume) |
South of Cheung Chau |
Marine
Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites)
& Type 2 ¡V Confined Marine Disposal) , m3 |
1283 |
111915 (Bulk volume) |
East of Sha Chau |
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (
5.5.5.
Inert and non- inert C&D waste were disposed of
in this reporting month. Details of the waste flow table are summarized in Table
5.21
Table 5.21 Details of Waste Disposal for Contract no. HY/2009/15
Waste
Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert
C&D materials disposed, m3 |
13847.2 |
131992.4 |
Tuen Mun Area 38 |
31978.9 |
32930.1 |
TKO137 FB |
|
Inert
C&D materials recycled, m3 |
NIL |
184.0 |
To Contract HY/2009/11 |
NIL |
304 |
ex-PCWA |
|
NIL |
109 |
TS4 |
|
Non-inert
C&D materials disposed, m3 |
15.0 |
205.6 |
SENT Landfill |
Non-inert
C&D materials recycled, kg |
137478 |
151443 |
N/A |
Chemical
waste disposed, kg |
200 |
8,200 |
N/A |
Marine
Sediment (Type 1 ¡V Open Sea Disposal), m3 |
NIL |
33,427 (Bulk Volume) |
South of Cheung Chau |
Marine
Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined
Marine Disposal) , m3 |
10440 |
169252 (Bulk Volume) |
East of Sha Chau |
Marine Sediment (Type 3 ¡V Special Treatment / Disposal
contained in Geosynthetic Containers) |
NIL |
7,050 (Bulk Volume) |
East of Sha Chau |
Contract no. HK/2010/06 - Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass over MTR Tsuen Wan Line
5.5.6.
Inert C&D waste was disposed of in this
reporting month. Details of the waste flow table are summarized in Table
5.22.
Table 5.22 Details of Waste Disposal for Contract no. HK/2010/06
Waste
Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert
C&D materials disposed, m3 |
1008 |
10037.83 |
TM38 |
Inert
C&D materials recycled, m3 |
NIL |
NIL |
N/A |
Non-inert
C&D materials disposed, m3 |
NIL |
NIL |
N/A |
Non-inert
C&D materials recycled, kg |
200 |
661.5 |
N/A |
Chemical
waste disposed, L |
0 |
600 |
N/A |
Marine
Sediment (Type 1 ¡V Open Sea Disposal), m3 |
0 (Bulk Volume) |
3,297 (Bulk Volume) |
South Cheung Chau |
Marine
Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined
Marine Disposal) , m3 |
0 (Bulk Volume) |
12,297 (Bulk Volume) |
|
There were no marine sediments Type 1 ¡V Open Sea Disposal (Dedicate Sites) &
Type 2 ¡V Confined Marine Disposal dredging from bore-piling casing in the reporting month.
Contract no. HY/2009/19 ¡VCentral- WanChai Bypass Tunnel (North Point Section)
and Island Eastern Corridor Link
5.5.7.
There is no project-related waste disposal in the
reporting month.
6.0.1.
The Event Action Plan for construction noise, air
quality and water quality are presented in Appendix 6.1.
Contract
no. HY/2009/11 ¡V Central ¡V Wanchai Bypass, North Point Reclamation
6.1.1
No exceedance was recorded in the reporting month.
Contract
no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at
HKCEC
6.1.2
No exceedance was recorded in the reporting month.
Contract no. HK/2009/02 -
Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
6.1.3
No exceedances was recorded in the reporting month.
Contract no. HY/2009/15 -
Central-Wanchai Bypass ¡V Tunnel (
6.1.4
No exceedances was recorded in the reporting month.
Contract no. HK/2010/06 -
Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass over MTR Tsuen Wan Line
6.1.5
No exceedance was recorded in the reporting month.
Contract
no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under FEP-07/364/2009/A
6.1.6
Three limit level exceedances were recorded at M6 ¡V
HK Baptist Church Henrietta Secondary School on 28 February, 13 and 27 March
2012 in the reporting month. Investigation
found that major traffic noise was contributed in the noise monitoring and not
related to the Project.
6.2.1.
No
project-related exceedance was recorded in real-time noise monitoring in the
reporting month.
6.3.1.
No exceedance was recorded in 1-hr TSP and 24 hrs
TSP monitoring in the reporting month.
Contract
no. HY/2009/11 ¡V Central ¡V Wanchai Bypass, North Point Reclamation
6.4.1
No exceedance was recorded in the reporting month.
Contract
no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at
HKCEC
6.4.2
Exceedances of turbidity and SS level were recorded
at WSD7, WSD19 and WSD20. Checked with Contractor's works, the deployed silt
screen and silt curtain were in proper condition for the dredging works at
HKCEC water channel. In view that the silt screen and silt curtain were in
proper condition, these exceedances were considered no related to Project work.
6.4.3
One SS exceedances recorded at C3 on 19 March 2012.
Investigation found that the condition of silt screen and silt curtain was in
proper conditions for the dredging works at CH240 in water channel. Other than
that, Contractor¡¦s daily recorded were checked and no further exceedances was
recorded in the next consecutive monitoring. These exceedances were considered
no related to Project work.
Contract no. HK/2009/02 -
Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
6.4.4
Occasional turbidity and SS exceedances at mid-ebb
and mid-flood were recorded at C5e, C5w,WSD17 and WSD21 in this reporting
month. After checking with Contractor, the deployed silt screen at intake and
silt curtain at western temporary sheet pile were observed to be in proper
condition for the marine construction works during the water quality
monitoring, and Contractor has provided all the necessary mitigation measures
to ensure the marine water quality. These
exceedances were considered not related to the Projects works.
Contract no. HY/2009/15 -
Central-Wanchai Bypass ¡V Tunnel (
6.4.5
One turbidity exceedance recorded at C7 on 23 March
2012. Investigation found that the condition of silt screen and silt curtain
was in proper conditions for the rockfilling of seawall construction at the SW
corner of CBTS. Other than that, Contractor¡¦s daily recorded were checked and
no further exceedance was recorded in the next consecutive monitoring. This
exceedance was considered no related to Project work.
Contract no. HK/2010/06 -
Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass over MTR Tsuen Wan Line
6.4.6
No exceedance was recorded in the reporting month.
Contract no. HY/2009/19-
Central- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor
Link
6.4.7
Occasional turbidity and SS exceedances at mid-ebb
and mid-flood were recorded at C8 and C9 in this reporting month. Investigation
revealed that there are numerous unknown outfalls from the nearby coastal area
closed to the cooling intakes C8 and C9, it causes the potential for
accumulation of pollutants near the intakes and may lead to potential water
quality deterioration at the seawater intake points. The exceedances were
considered as non project- related.
6.4.8
Summary for notification of exceedances can be
referred to Appendix 6.2.
6.5.1.
There was no non-compliance from the site audits in
the reporting period. The observations and recommendations made in each
individual site audit session were presented in Section 8.
6.6.1.
There was no particular action taken since no
project-related non-compliance was recorded from the site audits and
environmental monitoring in the reporting period.
7.0.1.
According to Condition 3.4 of the EP-356/2009, this
section addresses the relevant cumulative construction impact due to the concurrent
activities of the current projects including the Central Reclamation Phase III,
Central-Wanchai Bypass and Island Eastern Corridor Link projects.
7.0.2.
Monthly
EM&A report (March 2012) of Central Reclamation Phase III (CRIII) is
outstanding in this reporting period, no cumulative construction impact due to
the concurrent activities of the current projects with the Central Reclamation
Phase III (CRIII) could be done.
7.0.3.
According to the construction programme of Wan Chai
Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link
projects, the major construction activities at Reclamation Shoreline Sub-zones
under Wan Chai Development Phase II were the dredging and filling at HKCEC3w,
dredging at submarine sewage pipelines, reinstatement of seawall block
construction at TCBR1W and marine bored piling at MTR Tunnel Crossing in the
reporting month. The major environmental impact was water quality impact at,
7.0.4.
The major environmental impacts generated from the reclamation
work at Central Reclamation Phase III were only located along the coastline of
Central and Admiralty. As no project related exceedance was recorded in the
Project, it was considered no adverse environmental impact caused by the
Project works. Thus, it is evaluated the cumulative construction impact was
insignificant.
8.0.1.
During this reporting month, weekly environmental
site audits were conducted for Contracts no. HK/2009/01, HK/2009/02, HY/2009/15,
HK/2010/06 and HY/2009/19. No non-conformance was identified during the site
audits.
8.0.2.
Five site inspections for Contract no. HK/2009/01
were carried out on 29 February 2012, 7, 14 and 22 March 2012 in reporting
month. Results of these inspections and outcomes are summarized in Table 8.1.
Table
8.1 Summary of
Environmental Inspections for Contract no. HK/2009/01
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
120229_01 |
29-Feb-12 |
Sand
bags for gully protection were broken (Northern Gate under
HKCEC) |
Replacement
of sandbags for gully protection. |
Completion
as observed on 7-Mar-12 |
120307_01 |
7-Mar-12 |
Stockpile
was placed too close to the seawall (west side of HKCEC) |
Removal
of stockpile near the seawall. |
Completion
as observed on 14-Mar-12 |
120314_01 |
14-Mar-12 |
The
tree (no.T0656) located in TST was not surrounded by tree protection zone. |
Tree protection zones should be provided. |
Completion
as observed on 22-Mar-12 |
120314_02 |
14-Mar-12 |
The
floating debris was observed on the water channel (HKCEC). |
Removal
of rubbish from sea surface at regular intervals. |
Completion
as observed on 22-Mar-12 |
120322_01 |
22-Mar-12 |
The
oil stains were observed in A4-2. |
The oil stains should be removed and
provide a better
maintenance of plants. |
Completion
as observed on 28-Mar-12 |
8.0.3.
Four site inspections for Contract no. HK/2009/02
were carried out on 1, 8, 16 and 21 March 2012 during this reporting period.
The results of these inspections and outcomes are summarized in Table 8.2.
Table
8.2 Summary of
Environmental Inspections for Contract no. HK/2009/02
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
120308_01 |
8-Mar-12 |
The
water from U-channel should be cleaned more regularly. |
Keeping
the u-channel clear. |
Completion
as observed on 16-Mar-12 |
120316_01 |
16-Mar-12 |
The broken tarpaulin for the transfer of sediment from barge was observed. (WCR1) |
Replacement
of tarpaulin. |
Completion
as observed on 21-Mar-12 |
120316_02 |
16-Mar-12 |
The
leakage of sediment out the silt curtain was observed .(WCR1) |
Maintenance
of silt curtain. |
Completion
as observed on 21-Mar-12 |
120316_03 |
16-Mar-12 |
The chemical container was not provided with drip
tray.
WCR1. |
Provided
drip tray for chemical storage. |
Completion
as observed on 21-Mar-12 |
120321_01 |
21-Mar-12 |
Cement
mixing plant was not covered by 3 sides
enclosure,
including the top, with tarpaulin. (small pet park) |
Provided
adequate cover for cement mixing plant. |
Completion
as observed on 28-Mar-12 |
8.0.4.
Four site inspections for Contract no. HY/2009/15
were carried out on 28 February 2012, 6, 13, 20 and 27 March 2012 in reporting
month. The results of these inspections and outcomes are summarized in Table
8.3.
Table
8.3 Summary of
Environmental Inspections for Contract no. HY/2009/15
Date |
Observations |
Action taken by Contractor |
Outcome |
|
120228_01 |
28-Feb-12 |
The slopping seawall was observed (Eastern seawall). |
The condition of slopping seawall
should be improved. |
Completion as observed on 6-Mar-12 |
120228_02 |
28-Feb-12 |
Stockpile near to the seawall edge
was observed (TS1). |
The
stockpile should be cleaned away from the seawall edge. |
Completion as observed on 6-Mar-12 |
120313_01 |
13-Mar-12 |
Oil leakage was found from a
generator (TS1). |
The contractor should collect the
contaminated top soil and repair the plant prior re-use. |
Completion as observed on 20-Mar-12 |
120313_02 |
13-Mar-12 |
The poor protection of the slopping seawall was observed (TS4). |
The
landing area of cement truck should be improved or paved. |
Completion as observed on 20-Mar-12 |
120320_01 |
20-Mar-12 |
The
poor protection of slopping seawall was observed (TS1), |
The geotextile should be better
maintained and external silt curtain should be provide ASAP. |
Completion as observed on 27-Mar-12 |
120327_01 |
27-Mar-12 |
There
was no tarpaulin during stockpile removal operations.(TS1) |
Tarpaulin should be placed between barge and seawall |
Completion as observed on 3-April-12 |
120327_02 |
27-Mar-12 |
Geotextile of slopping sea wall was in poor condition. |
Geotextile of slopping sea wall
should be better maintained. |
Completion as observed on 3-April-12 |
8.0.5.
Four site inspections for Contract no. HK/2010/06
were carried out on 5, 12, 22 and 26 March 2012 in reporting month. The results
of these inspections and outcomes are summarized in Table 8.4.
Table 8.4 Summary
of Environmental Inspections for Contract no. HK/2010/06
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
120305_01 |
5-Mar-12 |
The silt accumulated on the
U-channel. |
The
silt from U-channel should be cleaned
regularly |
Completion as observed on 12-Mar-12 |
120305_02 |
5-Mar-12 |
Minor
mixing of marine sediment and inert C&D materials at barge. (ª÷¶¶1¸¹) |
The
mixing of marine sediment and inert C&D materials at barge should be
avoided. |
Completion as observed on 12-Mar-12 |
120305_03 |
5-Mar-12 |
The floating debris inside the
silt curtain was observed. |
The
floating debris should be cleaned regularly. |
Completion as observed on 12-Mar-12 |
120322_01 |
22-Mar-12 |
The oil stain from generator was
observed. |
The oil
stain should be cleared and disposed as
chemical waste. Also, the drain hole should be plugged properly. |
Completion as observed on 26-Mar-12 |
8.0.6.
Four site inspections for Contract no. HY/2009/19
were carried out on 29 February 2012, 7, 14 and 21 March 2012 in reporting
month. The results of these inspections and outcomes are summarized in Table
8.5.
Table
8.5 Summary of Environmental
Inspections for Contract no. HY/2009/19
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
120307_01 |
7-Mar-12 |
The
poor condition of silt curtain was observed. |
Silt curtain should be well
maintained to avoid holes, gaps and floating.(All platforms) |
Completion as observed on 14-Mar-12 |
120321_01 |
21-Mar-12 |
Muddy water from wheelwash. was observed in the sea |
Although contractor has taken
immediate action to recitify the situation, they are still reminded that runoff should not be found out of
site area. |
Completion as observed on 28-Mar-12 |
9.0.1.
There was no complaint received in this reporting
month.
9.0.2.
The details of cumulative complaint log and updated
summary of complaints are presented in Appendix 9.1.
9.0.3.
Cumulative statistic on complaints and successful
prosecutions are summarized in Table 9.1 and Table 9.2
respectively.
Table
9.1 Cumulative Statistics on Complaints
Reporting Period |
No. of Complaints |
Commencement works (Mar 2010) to last
reporting month |
25 |
Mar 2012 |
0 |
Project-to-Date |
25 |
Table
9.2 Cumulative Statistics on Successful
Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this month (Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
10.0.1. The
EM&A programme was carried out in accordance with the EM&A Manual
requirements, minor alterations to the programme proposed were made in response
to changing circumstances.
10.0.2.
WDII/RSS
advised that the dredging works for submarine pipeline at
10.0.3.
Water
quality monitoring at WSD10 and WSD15 will be temporary suspended while water
quality monitoring at WSD9 and WSD17 were implemented with respect to
HK/2009/02 for the water quality monitoring scheduled on 8 Feb 12 onwards;
10.0.4.
Water
quality monitoring at C8 and C9 have been implemented with respect to
HY/2009/19 since the marine bore
piling work started on 28 January 2012.
10.0.5.
Based
on the safety concern when external façade refurbishment was conducted by contractor
employed by Provident Center (C9) between 9 January 2012 to 30 July 2012 which
caused to the inaccessibility of sampling either land and marine since 3 Feb
2012, there is a fine adjustment of the sampling location of water quality
monitoring at C9 since 10 March 2012 to the closest accessible point prior to
the completion of the external façade refurbishment work.
10.0.6.
With respect to the trial
dredging at WCR2 was scheduled on 20, 22, 24, 25 March and 1, 3 Apr 2012,
on-going water quality monitoring results at WSD21 during this period was
checked and indicated that there was no contribution due to the trial dredging
operation. Enhanced review of water quality around WCR2 was also
implemented and no deterioration in the water quality was observed.
10.0.7. The
scheduled construction activities and the recommended mitigation measures for
the coming month are listed in Table 10.1.
Table 10.1 Construction
Activities and Recommended Mitigation Measures in
Coming Reporting Month
Contract
No. |
Key
Construction Works |
Recommended
Mitigation Measures |
HK/2009/01 |
Marine
Works ¡P
Dredging for CH160 to CH260 for subsequent reclamation within HKCEC
water Channel ¡P
Reclamation works and installation of sheet pile water channel (from
CH170 to CH260) would be commenced upon completed of dredging form CH160 to
CH260 within HKCEC water Channel. ¡P
Rockfilling within HKCEC Water Channel (form CH220 to CH260) ¡P
Seawall reinstatement at WC landfall section ¡P
Dredging form CH290 to CH400 (stage 3) near ¡P
Installation of excavation and lateral support for modification of
vertical seawall near Cross-harbour Watermains Installation ¡P
Ground treatment works along the pipe pile wall at TST seafront
anticipated to be completed. ¡P
Trench excavation and installation of shoring system along the pipe
pile wall at TST seafront would be continued and anticipated ¡P
Installation of cross-harbor watermains nos. A17/B17 ¡P
Rockfilling protection works for cross-harbour watermians in Fresh Watermains, cooling watermains and salt watermains (On Land) ¡P
Works would be continued at Zone B1-3, B1-6, B4-4, A1-1, A3-3, A3-4B,
A3-5B,and A4-2A. ¡P
Trench excavation at Zone B5-3 and the subsequent trench excavation at
Zone B5-3B and B5-2B ¡P
Trench excavation at Zone B2-1
after the Third Term Chief Executive Election held at HKCEC. ¡P
Mainlaying works at Zone B1-3 and Zone B1-6 ¡P
Jacking pit construction at Zone A1-3 ¡P
Heading No. H6 (toward western direction) ¡P
Mainlaying works at Zone A2-2. ¡P
Heading No. 6 (toward eastern direction) after a jacking pit was
completed at A2-2. ¡P
Mainlaying works at traffic island near junction between ¡P
Heading Nos. H7 and H8 ¡P
Cable ducting works at |
¡P
To conform the installation and setting as in the silt
screen deployment plan ¡P
Frequency spray water on the dry dusty road and on the
surface of concrete breaking ¡P
To cover the dusty material or stockpile by impervious
sheet ¡P
To space out noisy equipment
and position as far as possible from sensitive receiver. ¡P
To well maintain the mechanical
equipments / machineries to avoid abnormal noise nuisance. ¡P
Machines and plant that may be
in intermittent use should be shut down between work periods or should be
throttled down to a minimum ¡P
Daily visual inspection of silt screen and silt curtain to
ensure its operation properly |
HK/2009/02 |
¡P
Continue operation of Tseung Kwan O Public Fill Sorting Facility. ¡P
Continue E&M works and ABWF works of passenger terminal. ¡P
Continue the T&C work of passenger terminal. ¡P
Continue remaining 300mm thick slab construction, foam system,
lighting, oil interceptor and guard house installation and E&M works at ¡P
Continue Noise Barrier NB1 and NB2 main frame and panel installation
at ¡P
Continue d steel platforms installation at -0.85mPD for P8 & P9
Pumping Stations. ¡P
Continue steel platforms (Wet Well) installation at +2.2mPD for P7, P8
& P9 Pumping Stations. ¡P
Completed DSD 1 pipe jacking drive in TBM. ¡P
Commence DSD 2 pipe jacking drive in TBM. ¡P
Continue trench excavation and pipe laying works along ¡P
Continue trenchless excavation for the cooling mains connection between
¡P
Complete construction from + 11.63mPD to + 15.71mPD or WSD Salt Water
Pumping Station. ¡P
Continue 800MS pipe installation inside ¡P
Continue 800MS jacking pit excavation for the crossing under ¡P
Continue ABWFs & E&M works of WSD Salt Water Pumping Station. ¡P
Continue excavation works of seaside cofferdams for salt water intake
culvert, submarine outfall and Box Culvert N1. ¡P
Continue excavation works of landside cofferdam for the construction
of Bay 6 ¡V 10 salt water intake culverts. ¡P
Continue substructure works for the New Ferry Pier at Portions 1A, 2A,
2B, 2C & 3C. ¡P
Complete the fabrication of precast slabs for the New Ferry Pier in
PRC casting yard. ¡P
Installation of precast domes and end caps at the diffuser section of
the HDPE pipelines. ¡P
Complete backfilling rockfills for the installed submarine outfall
pipes and diffuser section and commence precast dome installation. ¡P
Continue installation of the temporary water diversion piping at WCR2
area. ¡P
Complete pre-bored H-piles construction at Box Culvert O |
¡P
To cover the dusty material or stockpile by impervious
sheet; ¡P
Frequency spray water on the dry dusty road and on the
surface of concrete breaking ¡P
To well maintain the mechanical equipments / machineries
to avoid abnormal noise nuisance and dark smoke emission ¡P
To conform the installation and setting as in the silt
screen and silt curtain deployment plan ¡P
Movable noise barrier shall be
deployed for demolition works ¡P
Daily visual inspection of silt screen and silt curtain to
ensure its operation properly ¡P
Review silt screen deployment
and silt curtain deployment and resubmit associate plans to EPD ¡P
Implement silt screen and silt
curtain in accordance with the associated plans submitted to EPD. |
HY/2009/15 |
¡P
Diaphragm wall
construction at TS4 ¡P
ELS works at TS1
and TPCWAE ¡P
Night time
protection works at CHT ¡P
Cut off wall
preparation works at ¡P
Dredging for
seawall foundation at TS2 |
¡P
Watering
any dust generating activities ¡P
Checking
all drip trays frequently and clear any stagnant water and mud inside it. ¡P
Noise
control measures shall be provided during restricted hours. |
HK/2010/06 |
¡P
Installation of bored pile
casing ¡P
Excavation of bored piles ¡P
Concreting of bored piles ¡P
Coring works |
¡P
To conform the installation and setting as in the silt
screen and silt curtain deployment plan ¡P
To space out noisy equipment
and position as far as possible from sensitive receiver. ¡P
Daily visual inspection of silt screen and silt curtain to
ensure its operation properly |
HY/2009/19 |
¡P
Marine Bored Piling |
¡P
To conform the installation and setting as in the silt
screen and silt curtain deployment plan |